A. A generator shall request a generator
identification number on a form provided by the Director, and shown as Appendix
A to this Article, prior to shipping special waste. Within 30 days of receiving
the completed form, the Director shall issue the identification number to the
generator.
B. Prior to off-site
consignment of special waste, the generator shall do all of the following:
1. Complete and sign the "Generator" section
of a special waste manifest.
2.
Obtain the handwritten signature of the special waste shipper on the special
waste manifest.
3. Retain the
generator's copy of the special waste manifest.
4. Give the special waste manifest and the
remaining attached copies to the special waste shipper or forward it to the
receiving facility.
C.
Within 14 days after shipment was accepted by a special waste shipper for
off-site consignment, the generator shall submit to the Director one legible
copy of each special waste manifest with the generator's section completed and
containing signatures of the generator and special waste shipper.
D. If, within 35 days after the date the
waste was accepted by the initial special waste shipper, the generator does not
receive a completed copy of this special waste manifest with the handwritten
signature of the special waste receiving facility operator, the generator shall
contact the special waste shipper and the special waste receiving facility
operator to determine the status of the special waste.
E. The generator shall submit an exception
report to the Director if the generator does not receive a completed, signed,
legible copy of the special waste manifest within 45 days of the date the waste
was accepted by the initial special waste shipper for off-site consignment. The
exception report shall contain both of the following:
1. A cover letter, signed by the generator,
which explains the efforts made to locate the special waste and the results of
those efforts.
2. A legible copy of
the special waste manifest which was signed by the generator and the special
waste shipper and retained by the generator.
F. The generator shall retain a legible copy
of each signed special waste manifest for at least three years from the date of
acceptance of a shipment of special waste for off-site consignment.
G. If a person is required to have a
manifest, shipping paper or shipping record under federal law for the special
waste, the federal manifest, shipping paper, or shipping record may be used in
lieu of the Arizona special waste manifest form so long as the federal
manifest, shipping paper, or shipping record includes all the information
required on the Arizona special waste manifest form.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.