A. PCS from one
or more points of generation under the control of a single generator may be
accumulated in an accumulation site under the control of that generator for up
to 90 days prior to shipment of the PCS to a storage, disposal, or treatment
facility.
B. An accumulation site
shall comply with the storage facility requirements set forth in
R18-13-1611, except subsection (A)
of that Section. An accumulation site shall not be required to comply with the
requirements in
R18-13-1607.
C. While PCS is at an accumulation site, the
owner or operator shall control public access and prevent unauthorized
vehicular traffic and illegal dumping. PCS shall be managed to prevent the PCS
from being exposed to storm water run-on or run-off.