Ariz. Admin. Code § R18-15-303 - Drinking Water Revolving Fund Project Priority List
A. The Authority annually shall prepare a
Drinking Water Revolving Fund Project Priority List as part of the Intended Use
Plan described in
R18-15-302 . The Board may waive
the requirement to develop an annual Drinking Water Revolving Fund Project
Priority List if funds are not adequate to assist any projects or if the Board
determines that no financial assistance will be offered for the annual funding
cycle.
B. An applicant pursuing
financial assistance from the Authority for a project shall request to have the
project included on the Drinking Water Revolving Fund Project Priority List.
The applicant may request that multiple projects be placed on the Drinking
Water Revolving Fund Project Priority List. An applicant shall make a request
for placement of a project on the Drinking Water Revolving Fund Project
Priority List on or before a date specified by the Authority and in an
application format specified by the Authority. The Authority shall include with
the project priority list application form the criteria under each ranking
category in
R18-15-304(A) by
which the project will be evaluated and the relative importance of each of the
criterion.
C. In preparing the
Drinking Water Revolving Fund Project Priority List, the Authority shall
consider all project priority list applications submitted under subsection (B).
The Authority shall evaluate the merits of each project with respect to water
quality issues and determine the total points of each project according to
R18-15-304 . At a minimum, the
Drinking Water Revolving Fund Project Priority List shall identify:
1. The applicant;
2. Project title;
3. Type of project;
4. Population of service area;
5. The amount requested for financial
assistance;
6. The subsidy
according to
R18-15-304(C);
7. Whether the project is within the fundable
range according to
R18-15-305; and
8. The rank of each project by its total
points, determined according to
R18-15-304.
D. After adoption of the annual Intended Use
Plan and project priority list according to
R18-15-302, the Board may allow:
1. Updates and corrections to the adopted
Drinking Water Revolving Fund Project Priority List, if the updates and
corrections are adopted by the Board after public notice; or
2. Additions to the Drinking Water Revolving
Fund Project Priority List, if the additions are adopted by the Board after
public notice.
E. After
public notice, the Board may remove a project from the Drinking Water Revolving
Fund Project Priority List under one or more of the following circumstances:
1. The recipient has received all financial
assistance identified in the executed financial assistance agreement with the
Authority;
2. The project was
financed from another source;
3.
The project is no longer an eligible project;
4. The applicant requests removal;
5. The applicant is no longer an eligible
applicant; or
6. The applicant did
not update, modify, correct or resubmit a project from the project priority
list developed for the previous funding cycle.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.