Ariz. Admin. Code § R18-2-716 - Standards of Performance for Existing Coal Preparation Plants
A. The provisions
of this Section are applicable to any of the following affected facilities in
coal preparation plants: thermal dryers, pneumatic coal-cleaning equipment,
coal processing and conveying equipment including breakers and crushers, coal
storage systems, and coal transfer and loading systems. For purposes of this
Section, the definitions contained in
40
CFR 60.251 are adopted by reference and
incorporated herein.
B. No person
shall cause, allow or permit the discharge of particulate matter into the
atmosphere in any one hour from any existing coal preparation plant in total
quantities in excess of the amounts calculated by one of the following
equations:
1. For process sources having a
process weight rate of 60,000 pounds per hour (30 tons per hour) or less, the
maximum allowable emissions shall be determined by the following equation:
E = 4.10P0.67
where:
E = the maximum allowable particulate emissions rate in pounds-mass per hour.
P = the process weight rate in tons-mass per hour.
2. For process sources
having a process weight rate greater than 60,000 pounds per hour (30 tons per
hour), the maximum allowable emissions shall be determined by the following
equation:
E = 55.0P0.11 -40
where "E" and "P" are defined as indicated in subsection (B)(1).
C. Actual values shall be
calculated from the applicable equations and rounded off to two decimal
places.
D. For purposes of this
Section, the total process weight from all similar units employing a similar
type process shall be used in determining the maximum allowable emission of
particulate matter.
E. Fugitive
emissions from coal preparation plants shall be controlled in accordance with
R18-2-604 through
R18-2-607.
F. The test methods and procedures required
by this Section are as follows:
1. The
reference methods in the 40 CFR 60, Appendix A, as incorporated by reference in
Appendix 2 of this Chapter, are used to determine compliance with standards
prescribed in subsection (B) as follows:
a.
Method 5 for the concentration of particulate matter and associated moisture
content,
b. Method 1 for sample and
velocity traverses,
c. Method 2 for
velocity and volumetric flow rate,
d. Method 3 for gas analysis.
2. For Method 5, the sampling time
for each run shall be at least 60 minutes and the minimum sample volume is 0.85
dscm (30 dscf) except that short sampling times or smaller volumes, when
necessitated by process variables or other factors, may be approved by the
Director. Sampling shall not be started until 30 minutes after start-up and
shall be terminated before shutdown procedures commence. The owner or operator
of the affected facility shall eliminate cyclonic flow during performance tests
in a manner acceptable to the Director.
3. The owner or operator shall construct the
facility so that particulate emissions from thermal dryers or pneumatic coal
cleaning equipment can be accurately determined by applicable test methods and
procedures under subsection (F)(1).