Ariz. Admin. Code § R4-8-105 - Time-frames for Licensure, Certification, and Approval
A. For the purpose of A.R.S. §
41-1073, the Board establishes the time-frames listed in Table 1. An applicant or a
person requesting an approval from the Board and the Executive Director of the
Board may agree in writing to extend the substantive review and overall
time-frames by no more than 25% of the overall time-frame.
B. The administrative completeness review
time-frame begins when the Board receives an application packet or a request
for approval. During the administrative completeness review time-frame, the
Board shall notify the applicant or person requesting approval that the
application packet or request for approval is either complete or incomplete. If
the application packet or request for approval is incomplete, the Board shall
specify in the notice what information is missing.
C. An applicant or person requesting approval
whose application packet or request for approval is incomplete, shall submit
the missing information to the Board within the time to complete listed in
Table 1. Both the administrative completeness review and overall time-frames
are suspended from the date of the Board's notice under subsection (B) until
the Board receives all of the missing information.
D. Upon receipt of all missing information,
the Board shall notify the applicant or person requesting approval that the
application packet or request for approval is complete. The Board shall not
send a separate notice of completeness if the Board grants or denies a license,
certificate, or approval within the administrative completeness time-frame
listed in Table 1.
E. The
substantive review time-frame listed in Table 1 begins on the date of the
Board's notice of administrative completeness.
F. If the Board determines during the
substantive review that additional information is needed, the Board shall send
the applicant or person requesting approval a comprehensive written request for
additional information.
G. An
applicant or person requesting approval who receives a request under subsection
(F), shall submit the additional information to the Board within the time for
response listed in Table 1. Both the substantive review and overall time-frames
are suspended from the date of the Board's request until the Board receives the
additional information.
H. An
applicant or person requesting approval may receive a 30-day extension of the
time provided under subsection (C) or (G) by providing written notice to the
Board before the time expires. If an applicant or person requesting approval
fails to submit to the Board the missing or additional information within the
time provided under Table 1 or the time as extended, the Board shall close the
applicant's or person's file. To receive further consideration, an applicant or
person requesting approval whose file is closed shall re-apply.
I. Within the overall time-frame listed in
Table 1, the Board shall:
1. Grant a license,
certificate, or approval if the Board determines that the applicant or person
requesting approval meets all criteria required by statute and this Chapter;
or
2. Deny a license, certificate,
or approval if the Board determines that the applicant or person requesting
approval does not meet all criteria required by statute and this
Chapter.
J. If the Board
denies a license, certificate, or approval, the Board shall send the applicant
or person requesting approval a written notice explaining:
1. The reason for denial, with citations to
supporting statutes or rules;
2.
The applicant's or person's right to appeal the denial by filing an appeal
under A.R.S. Title 41, Chapter 6, Article 10;
3. The time for appealing the denial;
and
4. The applicant's or person's
right to request an informal settlement conference.
K. If a time-frame's last day falls on a
Saturday, Sunday, or official state holiday, the next business day is the
time-frame's last day.
Notes