Ariz. Admin. Code § R7-2-1100 - Construction Project Delivery Methods

A. For the design-bid-build project delivery method, the school district shall procure:
1. Design services pursuant to R7-2-1117 through R7-2-1123, except as authorized by R7-2-1053 and R7-2-1055.
2. Construction by competitive sealed bidding pursuant to R7-2-1021 through R7-2-1032 and R7-2-1102 through R7-2-1105, except as authorized by R7-2-1033, R7-2-1053, R7-2-1055, and R7-2-1101.
B. For construction-manager-at-risk, design-build and job-order-contracting project delivery methods, the school district shall procure construction services pursuant to R7-2-1102 through R7-2-1115.
C. For construction-manager-at-risk project delivery method, the school district shall purchase design services pursuant to R7-2-1117 through R7-2-1123.
D. For job-order-contracting project delivery method, the school district may include design services in the job-order-contracting construction services contract, but if the school district does not include design services in the contract, the school district shall procure any design services relating to construction services projects under the contract pursuant to R7-2-1117 through R7-2-1123.

Notes

Ariz. Admin. Code § R7-2-1100
Adopted by exempt rulemaking at 33 A.A.R. 1526, effective 7/1/2014.

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.