Ariz. Admin. Code § R7-6-503 - Funding for Land
A. A school
district that is approved for funding of a new school facility under
R7-6-502, may ask the Board to
provide funding to purchase land on which to locate the new school
facility.
B. The Board follows a
three-step process, as described in subsections (C) through (E), before
recommending whether to authorize funding to purchase land for construction of
a new school facility. The Director may deviate from the three-step process to
meet circumstances such as purchasing state-owned or condemned land. The
Director shall bring a recommendation regarding funding to purchase land to the
full Board.
1. A list of all land
parcels currently owned by the school district;
2. The size and location of each
district-owned land parcel; and
3.
Why each district-owned land parcel is not suitable for the needed new school
facility.
1. A
school district that requests to purchase a specific land site for construction
of a new school facility shall provide the following to the Board:
a. A map of the school district showing
current school facilities and, for each school facility, the projected student
population, grade levels served, and attendance boundaries;
b. A description the land site selection
process;
c. An explanation of why
the land site requested was chosen over alternative sites;
d. A summary of any joint-use provisions or
other intergovernmental agreements related to the land site requested;
and
e. The legal description, size,
and estimated cost of the requested land site. If the size of the requested
land site is outside the range of acreage table approved by the Board, the
school district shall justify the deviation.
2. The Board shall review the information
submitted under subsection (D)(1) and either authorize or deny authorization
for the school district to proceed to perform due diligence regarding the land
site the school district proposes to purchase.
1. A school district that needs funds to
verify, gather, and submit the information required under subsection (E)(2)
shall submit a cost estimate to the Board and the Board shall approve or
disapprove the request to a maximum of $30,000. The Board shall deduct any
funds advanced to a school district to verify, gather, and submit the
information required under subsection (E)(2) from the final amount authorized,
if any. Rather than allocating funds to the school district to verify, gather,
and submit information required under subsection (E)(2), the Board may contract
and pay directly for the services.
3.
After reviewing the information provided by the school district under
subsection (E)(2), the Board shall prepare a recommendation for the Division
regarding whether to authorize purchase of the requested land site. The Board
shall include in the recommendation the cost of the land site and applicable
closing costs.
4. If the Division
decides to authorize purchase of the requested land site, the Division shall
request a funding appropriation from the legislature.
G. Additional
matters.
1. A school district that receives
funds under subsection (E)(1) shall provide documentation to the Board of the
actual expenditures from the funds after the final distribution.
2. A school district that receives funding
under subsection (F) shall provide documentation to the Board of actual closing
costs after the final distribution.
3. If completion of due diligence reveals a
serious problem with the proposed site or if the actual cost of the requested
site exceeds the amount approved by the Board, the school district may repeat
the three-step process for a new site.