Ariz. Admin. Code § R9-15-109 - Liquidated Damages for Failure to Complete a Loan Repayment Contract
A. An awardee who
fails to complete the terms of the loan repayment contract shall pay to the
Department the liquidated damages owed under A.R.S. §§
36-2172(J) or
36-2175(I), as
applicable, unless the awardee receives a waiver of the liquidated damages
under R9-15-110.
B. Upon receiving notification or upon the
Department's determination that an awardee is unable or does not intend to
complete the terms of the awardee's loan repayment contract, the Department
shall:
1. Withhold loan repayment
funds,
2. Determine liquidated
damages owed, and
3. Notify the
awardee of the amount of liquidated damages owed.
C. An awardee shall pay the liquidated
damages to the Department within one year after the termination date of the
awardee's loan repayment contract or within one year after the end of a loan
repayment contract suspension approved according to
R9-15-107, whichever is
later.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.