Ariz. Admin. Code § R9-16-706 - Review Time-frames
A. For each
type of certificate or approval issued by the Department under this Article,
Table 7.1 specifies the overall time-frame described in A.R.S. §
41-1072(2).
1. An applicant and the Department may agree
in writing to extend the substantive review time-frame and the overall
time-frame.
2. The extension of the
substantive review time-frame and overall time-frame may not exceed 25% of the
overall time-frame.
B.
For each type of certificate or approval issued by the Department under this
Article, Table 7.1 specifies the administrative completeness review time-frame
described in A.R.S. §
41-1072(1).
1. The administrative completeness review
time-frame begins on the date the Department receives an application packet
required in this Article.
2. Except
as provided in subsection (B)(3), the Department shall provide written notice
of administrative completeness or a notice of deficiencies to an applicant
within the administrative completeness review time-frame.
a. If an application packet is not complete,
the notice of deficiencies shall list each deficiency and the information or
documentation needed to complete the application packet.
b. A notice of deficiencies suspends the
administrative completeness review time-frame and the overall time-frame from
the date of the notice until the date the Department receives the missing
information or documentation.
c. If
the applicant does not submit to the Department all the information or
documentation listed in the notice of deficiencies within 30 calendar days
after the date of the notice of deficiencies, the Department shall consider the
application packet withdrawn.
3. If the Department issues a certificate or
approval during the administrative completeness review time-frame, the
Department shall not issue a separate written notice of administrative
completeness.
C. For each
type of certificate or approval issued by the Department under this Article,
Table 7.1 specifies the substantive review timeframe described in A.R.S. §
41-1072(3), which
begins on the date the Department sends a written notice of administrative
completeness.
1. Within the substantive review
time-frame, the Department shall provide written notice to the applicant that
the Department approved or denied the application.
2. During the substantive review time-frame:
a. The Department may make one comprehensive
written request for additional information or documentation; and
b. If the Department and the applicant agree
in writing, the Department may make supplemental requests for additional
information of documentation.
3. A comprehensive written request or a
supplemental request for additional information or documentation suspends the
substantive review time-frame and the overall time-frame from the date of the
request until the date the Department receives all the information or
documentation requested.
4. If the
applicant does not submit to the Department all the information or
documentation listed in a comprehensive written request or supplemental request
for additional information or documentation within 30 calendar days after the
date of the request, the Department shall deny the certificate or
approval.
D. An applicant
who is denied a certificate or approval may appeal the denial according to
A.R.S. Title 41, Chapter 6, Article 10.