Any building wired for electricity. A
building "wired for electricity" consists of an electrical wiring system that
distributes energy to be used for equipment, lighting, or appliances in the
building. "Wired for electricity" also involves the proper installation,
operation, and existence of electrical outlets, switches, breakers, meter base
and different electrical circuits for the building.
15.
SERVICING OR FILLING
CONTAINERS
A. The filling of any
container which does not have an attached approval tag is prohibited.
B. The discharge end of the filling hose
shall be fitted with an approved valve and the operator shall control the
liquid flow with this valve.
C. The
liquid volume of the connection between the discharge hose outlet valve and the
consumer's system filling valve shall not exceed eight (8) ounces.
D. At least one attendant shall remain close
to the transfer connection from the time the connections are first made until
they are finally disconnected.
E.
No liquid transfer hose, pipe, or tubing containing more than eight (8) ounces
of liquid shall be vented to the atmosphere.
F. The vapor pressure in any container shall
not be lowered by blowing or venting to the atmosphere; however, where a
container used solely for farm implement or industrial service cannot be
adequately filled due to vapor pressure, the pressure may be reduced to
facilitate filling by venting to the atmosphere, providing this can be safely
performed in an open area without undue hazard to any building or surrounding
property, and there is no open flame or other source of ignition in the
area.
G. Mobile fuel tanks shall be
charged only in the open air.
H. No
underground container shall be filled or serviced unless the maximum allowable
working pressure of the container can be readily determined.
I. Where a customer's premises does not offer
safe and adequate facilities for turning a delivery or transport truck around,
it is recommended that the driver back into the driveway to fill the customer's
container.
J. When it becomes
necessary to service a container after dark, a vaporpro of type flashlight, or
other approved explosion-proof type lighting shall be used. The use of a
standard type flashlight is prohibited.
K. No container shall be filled that shows
evidence of improper or faulty installation, leakage, defective fittings; or
which is not equipped with a safety relief valve and liquid level
gauge.
17.
STORAGE
CONTAINERS
(The words "Storage Containers" shall be construed to mean all
vessels used for bulk storage and commercial storage of liquefied petroleum
gases.)
A. Containers used for bulk
storage, and commercial storage vessels located at cotton gins, rice dryers,
schools, hospitals, bottle filling plants, etc., having a capacity over two
thousand (2000) water gallons, shall be located not less than fifty (50) feet
from the nearest important building or group of buildings or line of adjoining
property which may be built on. They shall not be less than fifty (50) feet
from main line or passing track of a railroad, or public highway. Waiver of
this requirement may be made by the Director providing no undue hazards exist,
but in no case shall they be located closer than twenty-five (25) feet,
regardless of size of the container. EXCEPTION: Bulk storage containers used
for the transferring of liquefied petroleum gases into delivery trucks shall be
not less than four hundred (400) feet from any school, hospital, or other place
of public assembly.
B. Storage
containers shall be provided with substantial reinforced concrete footings and
foundations and shall be mounted on saddles in such a manner as to permit
expansion and contraction. Every container shall be so supported as to prevent
the concentration of excessive loads on the supporting portion of the shell.
Suitable means of preventing corrosion shall be provided on that portion of the
container in contact with the foundation or saddles. There shall be a resilient
cushion of road expansion, or other suitable material placed between the saddle
and tank to allow for minor imperfections in pier surface, to protect the tank
from corrosion and to act a lubricant in tank expansion and contraction. That
portion of the tank surface that is to be in contact with the pier, or saddle,
shall be painted with at least two (2) coats of red lead, or its equivalent,
before installing on the supports. Blueprints of approved-type footings, and
foundations may be obtained from the Board upon request. EXCEPTION: Containers
used for storage of Propane gas, not exceeding 2500 water gallon capacity, and
containers used for storage of Butane gas, not exceeding 3000 water gallon
capacity may be mounted on prefabricated concrete blocks, providing the design
has been reviewed and approved by the Director prior to installation.
C. Storage containers shall be equipped with
the necessary safety relief valves as outlined in the latest edition of
Pamphlet No. 58, National Fire Protection Association, and shall have direct
communication with the vapor space of the container. The discharge from the
safety relief valve shall be upward and unobstructed to the open air.
D. Safety relief valves shall be so arranged
that possibility of tampering will be minimized: if pressure setting or
adjustment is external, the relief valve shall be provided with approved means
for sealing adjustment.
E. No
shut-off valve shall be installed between the safety relief valves and the
container.
F. Loose-fitting caps,
or covers, shall be placed over the safety valves to prevent rain or other
substance from entering the valves.
G. Storage containers of all types shall be
equipped with suitable ground wire, excess flow check valves in the liquid and
vapor outlets, liquid level gauging device, safety relief valves, and vapor
pressure gauge graduated to not less than one and one-half (1 1/2) times the
designed working pressure of the container, but need not exceed 300 PSI. The
coupling for the excess flow check valve and vapor return valve on containers
of 1200 gallons capacity, and over, shall be not less than one and one-fourth
(1 1/4) inches standard pipe size. All piping shall be wrought iron or steel
and shall be at least extra heavy to the first hand shut-off valve. All piping
past the first hand shut-off valve shall be at least extra heavy (Schedule 80)
if joints are threaded, or threaded and back welded. At least single strength
(Schedule 40) shall be used if joints are welded, or welded and flanged. The
use of cast iron plugs or fittings is prohibited. Stop valves shall be placed
as near the outlet as possible on all liquid and vapor lines. The piping
leading to and from the excess flow check valves shall be sufficient in size to
prevent pressure drops reaching the point where the excess flow check valve
would not function, and in no case shall such piping be reduced in size between
the check valve and the first hand shut-off valve, but must be equal to, or
greater in size than that of the excess flow check valve outlet.
(1). Each LP-gas stationary storage
installation of 6,000 gallons or more, aggregate capacity, installed on or
after July 1, 1993, shall incorporate in its design bulkheads and emergency
shutoff valves (ESVs) for liquid and vapor transfer systems. NOTE: This section
shall not apply where the liquid transfer hose is connected directly to a 13/4
inch or less acme-threaded filler valve when such valve is installed directly
into the container.
(2). Bulkheads
shall be of concrete or steel and anchored sufficiently to prevent displacement
of piping and fittings in the event of a truck pull-away while the transfer
hose is connected.
(A). Piping through a
bulkhead shall be secured to the bulkhead to prevent shifting. Piping shall
terminate through the bulkhead with a Schedule 80 pipe collar and a 12 inch
length of Schedule 80 pipe and forged steel elbow between the bulkhead and hose
coupling.
(B). Bulkheads shall not
be less than 10 feet from a container.
(3). Emergency shutoff valves (ESVs) shall be
installed in fixed piping of the transfer system upstream of the bulkhead and
within four feet of the bulkhead with a flexible wire braided hose not more
than 24 inches installed between the ESVs and the bulkhead.
(A).ESVs shall be installed according to the
manufacturer's instructions.
(B).
ESVs shall incorporate all of the following means of closing.
(1). automatic shutoff through
thermal (fire) actuation using fusible elements with a melting point not to
exceed 250F;
(2). manual shutoff at
the installed location; and
(3).
manual shutoff from a remote location. Remote controls shall be connected to
each ESV. Emergency remote controls shall be conspicuously marked and shall be
located and maintained to be readily accessible in emergencies.
(4). Where the flow of LP-gas is in one
direction only, a backflow check valve may be used in lieu of an ESV in the
fixed piping, provided that the back-flow check valve has a metal-to-metal seat
or a primary resilient seat with a secondary metal seat not hinged with
combustible material.
(5). ESVs or
back-flow check valves shall be installed in the piping system in such a manner
that any break resulting from a pull-away will occur on the transfer hose side
of the bulkhead and the valves and piping on the container side of the bulkhead
will remain intact.
(6). The
bulkhead(s) and ESV's must be kept in proper working order at all times in
accordance with the manufacturer's instructions.
See Diagrams on page 96.
H. A safety relief valve shall be installed
between each pair of shut-off valves on all liquid lines to relieve into a safe
atmosphere, any excess pressure that may exist. The start-to-discharge pressure
shall not be less than 400 PSIG or in excess of 500 PSIG.
I. All bulk storage containers, regardless of
size and containers used for fuel purposes such as mounted on automobiles,
trucks, buses, tractors, or other mobile or portable equipment, regardless of
size, and all commercial and industrial storage containers exceeding 1200 water
gallon capacity shall be equipped with individual fittings: the use of domestic
compact head and fittings is prohibited.
J. Where two or more containers are connected
rigidly together in a battery, provisions shall be made in all liquid and vapor
manifolds for the expansion or contraction of the vessels or piping.
K. The operator shall be in attendance at all
times while the container, regardless of type, is being loaded or unloaded: the
operator shall be stationed close to point of cutoff at all times during
filling or unloading operation.
L.
Each opening in container exceeding a No.54 drill size, except safety relief
valves and gauging devices of the float, or equivalent type which do not
require flow for their operation, shall be equipped with an excess flow valve
or its equivalent.
M. The welding
or brazing of any malleable fitting is prohibited.
N. All pipe and fittings subjected to tank
pressure where buried underground shall be at least extra heavy (Schedule
80).
O. The installation of any
storage container underground, or the covering of any storage container with a
mound of earth, or other material, except containers designed to operate under
refrigerated or cryogenic conditions, is prohibited.
P. Gauge glasses of the columnar type shall
be restricted to filling plants where the fuel is withdrawn in the liquid phase
only. They shall be equipped with valves having metallic hand wheels, with
excess flow valves and with extra-heavy glass adequately protected with a metal
housing applied by the gauge manufacturer. They shall be shielded against the
direct rays of the sun. Gauge glasses of the columnar type are prohibited on
truck tanks, motor fuel tanks, and on containers used in domestic, commercial,
and industrial installations.
Q.
Any container where transfer of liquids is made from such container into
portable container such as tractors, skid tanks, and motor fuel tanks, shall be
located not less than thirty (30) feet from any residence or publicly occupied
building. This does not include DOT cylinders, as they must be filled by weight
at approved filling stations in compliance with Section 10, Par. C., and
located in compliance with Par. A. of this Section.
R. Storage containers shall be painted at the
time of installation with white or aluminum paint, or any other light colored
paint with equivalent, heat-reflective characteristics, and shall have painted
on both sides and both heads where readily visible the word "FLAMMABLE" in red
letters at least six (6) inches in height. Warning signs with the following
words, "No Smoking Or Open Flame Permitted Within Ten (10) Feet", shall be
painted on the container or a sign adjacent to the container in letters of at
least one and one-half (1 1/2) inches in height, in black or red, on a white or
aluminum background. Where considered necessary by a representative of the
Board, containers shall be adequately protected by a suitable guard rail to
protect vessel from moving vehicles or objects, a fence, or provisions made for
locking the service line valves to prevent pranksters or prowlers or
unauthorized persons from opening the valves, allowing gas to escape. The
premises around the container shall be maintained in good order. Combustible
matter of any type shall not be allowed to accumulate near the
container.
S. Electric motors and
switches or internal combustion engines used in connection with compressors or
pumps for loading and unloading at bulk plants shall be explosion-proof
type.
T. All containers used for
domestic and commercial purposes and first stage regulating equipment shall be
located outside of buildings, other than those especially provided for this
purpose, except DOT cylinders which may be used indoors under the following
conditions:
(1) If temporarily used for
demonstration purposes and the container has a maximum water capacity of 12
pounds.
(2) If used with a
completely self-contained gas hand torch or similar equipment, and the
container has a maximum water capacity of 2 1/2 pounds.
Where portability of containers is necessary, making their
location outside the building or structure impracticable, DOT Cylinders having
a capacity not in excess of 30 water gallons may be located for use but not for
storage inside the building or structure under the following conditions
(1) Where gas is used for industrial
processing or repair work in an industrial building or structure being employed
for industrial purposes.
(2) Where
temporarily used in the construction, repair, or improvement of buildings or
structures and their fixtures and equipment.
(3) Provided regulator is attached directly
to the cylinder valve or to a manifold connected to the cylinder valves and
that no more than three (3) cylinders are connected to any one manifold, in any
one room unless separated by at least fifty (50) feet.
(4) Cylinders shall not be located or used
where exposed to possible excessive temperature, physical damage or tampering
by unauthorized persons, and shall be removed to the outside when not in
use.
(5) Language adopted by
reference NFPA58 6.4.4.1.
Each individual container shall be located with respect to the
nearest important building or group of buildings, or line of adjoining property
which may be built on in accordance with, by reference, NFPA58 Table
6.4.1.1.
Table adopted by reference NFPA58 6.4.1.1
Figure adopted by reference NFPA58 A.6.4.1.1
Figure adopted by reference NFPA58 I.1 (a)
Figure adopted by reference NFPA58 I.1 (b)
Figure adopted by reference NFPA58 I.1 (c)
The distance between liquefied petroleum gas containers and any
anhydrous ammonia container shall be not less than 25 feet.
No liquefied petroleum gas container in excess of 30,000 water
gallon capacity shall be installed prior to approval by the Board.
Containers that have been in use for the storage of anhydrous
ammonia shall not be used for the storage of liquefied petroleum gases unless
that container has been completely emptied and made free of all anhydrous
ammonia. The container shall be completely refitted in accordance with the
rules and regulations of this Code.
U. Language adopted by reference NFPA58
6.4.1.3.
V. Language adopted by
reference NFPA58 6.4.4.3.
W.
Language adopted by reference NFPA58 6.4.4.4.
X. Language adopted by reference NFPA58 6.4.3
(1), (2), (3), and (4).
Figure adopted by reference NFPA58 A.6.4.3 (4) (a)
Figure adopted by reference NFPA58 A.6.4.3 (4) (b)
Y. Flexible hose for use with
liquefied petroleum gases shall consists of a hose with a minimum bursting
pressure of not less than twelve hundred fifty (1250) PSI. There shall be
etched, cast, or impressed on the hose at 5 foot intervals, or on a name plate
permanently attached thereto, the following information: (See also "Fit for
Service" section regarding replacement name plates).
L.P.G.
Bursting Pressure
Manufacturer's name or trade mark
Year of manufacture
Z. Each storage container used in connection
with a service station operation not exceeding 2000 water gallon capacity shall
be located not less than twenty-five (25) feet from any building group of
buildings and adjoining property lines which may be built upon. Storage
containers in excess of 2000 water gallon capacity shall not be located closer
than fifty (50) feet in relation to the above.
A.A. Readily ignitable material including
weeds, dry grass, etc., shall be removed within ten (10) feet of the container.
Where quantity of combustible material is large, it may be necessary that the
distance between the container and material exceed ten (10) feet.
B.B. The minimum distance between LP-Gas
containers and flammable or combustible liquid tanks or containers shall be not
less than twenty (20) feet.
C.C. No
bulk or commercial storage container shall be installed or moved and
reinstalled at any location prior to approval by the Director.
D.D. Railcar to cargo tank transfer (commonly
called Transloading) is allowable under the following conditions:
(1) Installation must be done in accordance
with NFPA58 guidelines;
(2)
Installation is limited to twenty-four (24) months and must be approved by the
Board;
(3) A Class 8 Permit must be
obtained; and
(4) Annual
inspections must be conducted.
E.E. Language adopted by reference NFPA58
6.4.4.2.
19.
INSTALLATION AND PAINTING OF CONTAINERS
A. Underground containers shall be coated or
protected to minimize corrosion. Any damage to the coating shall be repaired
before backfilling. Containers shall be set level and shall be surrounded by
earth or sand firmly tamped in place. Back-fill shall be free of rocks and
abrasives. The container shall be so lowered into place as to prevent abrasion
or other damage to the container or coating. Cathodic protection shall be
provided for the container. Underground containers that have been removed from
the ground shall not be reinstalled until they have been thoroughly cleaned,
inspected, and approved by a representative of the Board. All underground
containers that have been installed for a period of one (1) year or longer and
are removed from the ground to be reinstalled shall be equipped with a new
regulator.
The reinstallation of any underground Butane container that has
been removed from the ground for resale, change of user or ownership is
prohibited.
(1) Underground containers
constructed for a safe working pressure of 200 or 250 PSI may be removed from
the ground and reinstalled above-ground provided:
(a) The container has been thoroughly
cleaned, inspected, and approved for reinstallation by a representative of the
Board.
(b) The standpipe is reduced
to a length not in excess of eight (8) inches and properly threaded.
(c) The container is equipped with the
necessary safety relief valves to meet the current requirements of the National
Fire Protection Association for aboveground containers.
(d) Each container shall be installed on
adequate supports or saddles. The attachment of any fitting or other connection
to the container by the use of a welding process shall be performed by a welder
approved by a representative of the Board. Approval for the attachment of any
fitting or connection under this process shall be obtained prior to welding.
After welding, each fitting or connection shall be adequately tested for any
leakage.
B.
Aboveground containers shall be painted at the time of installation with a
light reflecting color equivalent to white or aluminum paint and shall be
maintained in good condition. Combustible material shall not be allowed to
accumulate near the container. Aboveground containers shall not be installed
underground; nor shall they be covered with any type material.
C. ASME container assemblies listed for
underground installation, including interchangeable aboveground underground
container assemblies may be installed underground as follows:
(1) The container shell shall be placed at
least 6 inches below grade unless the container might be subject to abrasive
action or physical damage from vehicular traffic within a parking lot area,
driveway, or similar area. In this case, a non-interchangeable underground
container shall be used and the container shell placed at least 18 in. below
grade or equivalent protection shall be otherwise provided, such as the use of
a concrete slab to prevent imposing the weight of a vehicle directly on the
container shell. Protection of the fitting housing, housing cover, tank
connections, and piping shall be provided to protect against vehicular
damage.
(2) Where containers are
installed underground within 10 ft. (3 m) where vehicular traffic may be
reasonably expected, such as driveways and streets or within a utility easement
subject to vehicular traffic, protection of the fitting housing, housing cover,
tank connections, and piping shall be provided to protect against vehicular
damage.
(3) Approved
interchangeable aboveground-underground container assemblies installed
underground shall not be placed with the container shell more than 12 in. below
grade.
(4) The portion of the
container to which the fitting cover or other connections are attached need not
be covered. The discharge of the regulator vent shall be above the highest
probable water level.
(5)
Containers shall be protected against corrosion for the soil conditions at the
container site by a method in accordance with good engineering practice.
Precaution shall be taken to prevent damage to the coating during handling. Any
damage to the coating shall be repaired before backfilling.
(6) Containers shall be set substantially
level on a firm foundation (firm earth may be used) and surrounded by earth or
sand firmly tamped in place. Backfill shall be free of rocks or similar
abrasives.
(7). Language adopted by
reference NFPA58 6.4.4.5.
(8).
Language adopted by reference NFPA58 6.4.2.3.
(9). Language adopted by reference NFPA58
6.4.2.1.
(10). Language adopted by
reference NFPA58 6.4.30.
Underground piping systems shall be installed with at least 18
inches of cover. The cover may be reduced to 12 inches if external damage to
the pipe is not likely to result. If a minimum of 12 inches of cover cannot be
maintained, the pipe shall be installed in conduit or bridged (shielded). The
pipe shall be graded at least one (1) inch in ten (10) feet and a drip shall be
provided at any point in the line of pipe where condensation may collect. All
drips shall be installed only in such location that they will be readily
accessible to permit cleaning or emptying. All piping under houses shall be
graded at least two (2) inches in ten (10) feet with proper drips at low points
where condensate may collect and shall be supported with hangers as outlined in
paragraph DD of this Section.
D. The use of an aboveground Butane container
to supply vapor directly to a gas consuming appliance without use of a
vaporizer or some other means of artificially vaporizing the liquid to vapor
form is prohibited. A pressure reducing regulator of either high or low
pressure type shall be installed at the service line outlet on all aboveground
and underground type installations. No gas in the vapor phase at tank pressure
shall be permitted in the system piping.
E. The piping between the container and the
several service openings shall not be less in size than that recommended in
Tables No. 1 and 2, Pages 80 and 81 of these regulations. Underground piping
shall in no case be less than one-half (1/2) inch in diameter.
F. The installation of a system for use with
liquefied petroleum gas at a public building or structure such as a school,
church, hospital, theater, motel, rest home, but not limited to, shall be
examined and tested under an air pressure of not less than twenty-five (25)
PSIG for a period of time commensurate or proportionate to the size and length
of the piping, but in no case shall the test be for a period of less than
thirty (30) minutes. The test shall be witnessed by the owner, user, or
representative thereof.
A Report of Installation on an approved type form, obtainable
from the Department, shall be completed at the time of installation, and
forwarded to the Board, by the dealer on the same date; separate and apart from
any and all other reports that may be required.
Upon receipt of the Report of Installation, a representative of
the Board shall, within a period of time not to exceed one hundred twenty (120)
days, make an inspection of the installation to determine that the container,
visible piping, and appliances are properly installed.
Any extension, change, or alteration in the system shall be
performed in accordance with the above procedure.
G. No piping may be buried under public
buildings, such as schools, churches, hospitals, theaters, motels, and rest
homes, but not limited to. All piping shall be installed aboveground and shall
be supported with hangers as outlined in paragraph DD of this Section.
EXCEPTION -Piping from the container to the building shall be installed
underground. When it is not practical to install piping below ground, adequate
protection suitable to the Board shall be provided where installed
aboveground.
H. DOT cylinders
(commonly called bottles) shall not be buried underground.
Containers shall be set upon firm foundations or otherwise
firmly secured; the possible effect on outlet piping from settling of the
container shall be guarded against by a flexible connection or special
fitting.
(1) Valves in the assembly of
multiple container systems shall be arranged so that replacement of containers
can be made without shutting off the flow of gas in the system.
Note: This provision is not to be construed as requiring an
automatic change-over device.
(2) Container valves and pressure regulating
equipment shall be protected against tampering when installed for
use.
(3) Valves and connections to
the containers shall be protected while in transit, in storage, and while being
moved into final utilization, as follows:
(a)
By setting into recess of container to prevent possibility of their being
struck if container is dropped upon a flat surface, or
(b) By ventilated cap or collar, fastened to
container, capable of withstanding blow from any direction equivalent to that
of a thirty (30) pound weight dropped four (4) feet. Construction must be such
that a blow will not be transmitted to valve or other connection.
(4) Language adopted by reference
NFPA58 6.4.4.3.
I. When
containers, regardless of type or size, are not connected to the system, the
outlet valves shall be kept closed tight or plugged, even though containers are
considered empty.
J. All piping
where subject to tank pressure shall be at least extra heavy (Schedule 80) to
the first hand shut-off valve. All other piping subject to tank pressure shall
be at least extra heavy (Schedule 80) if joints are threaded, or threaded and
back welded. At least single strength (Schedule 40) shall be used if joints are
welded and flanged.
K. Piping
covered in these regulations shall be wrought iron, steel, (either black or
galvanized), brass or copper pipe, polyethylene (PE) plastic pipe and tubing
(see par. 1), or seamless copper or other approved nonferrous metal tubing. All
iron or steel pipe shall be schedule 40 or schedule 80 pipe. Copper tubing may
be either grade (K) or (L). The use of conduit pipe is prohibited.
(1) Plastic (PE) pipe or tubing fabricated in
compliance with and meeting the requirements for ASTM D2513, specifications for
thermoplastic gas pressure pipe, tubing and fittings may be used for outside
piping; underground only within the following limitations:
(a) Plastic pipe, tubing and fittings shall
be used to distribute liquefied petroleum gas in the vapor state only, at a
pressure not to exceed twenty (20) PSIG.
(b) No portion of the pipe, tubing or
fittings shall extend or be exposed above-ground, but shall be installed not
less than (12) inches belowground.
(c) The installation or use of any plastic
pipe, tubing or fitting beneath any type building or structure is
prohibited.
(d) Heat-fusion or
mechanical joints shall be used when joining plastic (PE) pipe, tubing or
fittings. All fittings and attachments shall be of the permanent (onetime use
only) type.
(e) Heat-fusion joints
shall be made in accordance with qualified procedures which have been
established and proven by test to produce gas-tight joints at least as strong
as the pipe or tubing joined.
(f)
When compression type mechanical joints are used, the gasket material in the
fitting shall be compatible with the plastic piping and the gas distributed. An
internal tubular rigid stiffener shall be used in conjunction with the fitting,
and the stiffener shall be flush with the end of the pipe or tubing and extend
at least to the outside end of the compression fitting when installed. The
stiffener shall be free of rough or sharp edges and shall not be a force fit in
the plastic. A split tubular stiffener shall not be used.
(g) The installation shall be performed in
such a manner as to eliminate any undue stresses resulting from thermal
contraction. All joints, attachments and fittings shall be designed and
installed to effectively resist or sustain the longitudinal pull-out forces
resulting from thermal change in the piping or by external loading.
(h) Plastic pipe shall be provided with an
electrically continuous corrosion resistant tracer wire (min AWG 14) or tape
buried with the plastic pipe to facilitate locating. One end shall be brought
above ground at a building or riser.
L. Iron or steel pipe shall not be bent or
rolled. Where a change in directions is necessary, proper fittings shall be
used.
M. Screw fittings for use
with wrought iron or steel pipe shall be either malleable iron or steel
fittings and shall have a working pressure of not less than 300 psi gauge.
(WOG)
N. Pipe joints may be
screwed, flanged, or welded. Joints in copper or other non-ferrous tubing shall
be of either of the following types: flare, compression, soldered, sweated, or
welded. An air pressure test of not less than twenty-five (25) psi gauge shall
be applied to these connections for a period of not less than 30
minutes.
O. Valves used with
liquefied petroleum gas piping shall be of an approved type suitable for use
with liquefied petroleum gas. Valve seat material, packing, gaskets, etc.,
shall be of a type resistant to the action of liquefied petroleum gases in the
liquid phase. Every valve or gas cock shall be readily accessible for operation
or repair.
P. Gas appliances
burning not more than ninety (90) cubic feet per hour may be connected with
seamless metal tubing connectors meeting the following requirements:
(1) End fittings shall be screw type or union
type, permanently attached 'at the factory.
(2) The method of attaching such tubing
connectors to the house piping and the gas appliances shall not depend upon
separate ferrules, washers, gaskets, or other detachable parts for gas
tightness, nor shall such separate parts be used to establish and maintain the
methods of seal provided within the connector and fittings.
(3) The over-all length of such connectors
shall not exceed six (6) feet.
Q. After new piping is installed, all outlets
shall be capped and tested at a pressure of not less than twenty-five (25)
pounds per square inch air pressure for a period of not less than thirty (30)
minutes. There shall be no loss of pressure during this test.
(1) When an interruption of service occurs
because of an addition to the piping system, or an existing system has been
repaired or replaced, all additions, repaired, or replaced piping shall be
tested at a pressure of not less than twenty-five (25) pounds per square inch
air pressure for a period of not less than thirty (30) minutes. There shall be
no loss of pressure during this test.
(2) A manometer, pressure gauge, or
equivalent test shall be performed on an existing installation whenever there
is an interruption of service caused by an out of gas situation, or if the
dealer is servicing the system for the first time. Also, if servicing the
system for the first time, the dealer shall do a visible systems check to
insure the gas system is installed correctly. This shall be done before placing
the system in service.
**Interruption of service means systems which require repair,
replacement, or addition to the piping system as well as out of gas
systems*
(a)
i Existing installations in a single family
dwelling or small commercial building shall be tested between a minimum of 85%
and a maximum of 95% of the operating pressure of the system at the location of
the test. No gain or loss in pressure shall occur during this test for a period
of three (3) minutes.
ii Existing
installations in a larger piping application shall be tested between a minimum
of 85% and a maximum of 95% of the operating pressure of the system at the
location of the test. The duration of the test shall be not less than thirty
(30) minutes for each 500 cubic feet of pipe volume or fraction thereof. No
gain or loss in pressure shall occur during this test.
(b) An alternative test method may be used
for systems serving appliances that receive gas at pressures of ½ % psig
or less, by inserting a water manometer or pressure gauge into the system
downstream of the final system regulator, pressurizing the system with either
fuel gas or air to a test pressure of 9 inches + or -V2 in. w.c., and observing
the device for a pressure change. If fuel gas is used as a pressure source, it
is necessary to pressurize the system to full operating pressure, close the
container service valve, and then release enough gas from the system through a
range burner valve or other suitable means to drop the system pressure to 9 in.
+ or - V2 in. w.c. This insures that all regulators in the system are unlocked
and that a leak anywhere in the system is communicated to the gauging device.
No gain or loss of pressure shall occur during this test for a period of three
minutes. For larger piping systems, the duration of the test shall not be less
than thirty (30) minutes for each 500 cubic feet of pipe volume or fraction
thereof. No gain or loss in pressure shall occur during this test.
There shall be no gain or loss of pressure during these
tests.
(3)
If a pressure gain or loss is noted in any of the above test procedures, the
source of the leak must be determined and repaired immediately before the
system can be placed in operation.
R. A second test shall then be applied after
gas cocks and appliances have been connected. This test shall be made by
filling the lines with gas at operating pressure and shall be held long enough
to prove all connections free from leaks by the use of a soapy water test at
all connections. This test shall include the connections at the regulator and
service line valve.
(1) The piping system
shall withstand the test pressure specified without showing any evidence of
leakage or other defects. Any reduction of test pressures as indicated by
pressure gauge shall be deemed to indicate the presence of a leak unless such
reduction can be readily attributed to some other cause.
(2) The leakage shall be located by means of
an approved combustible gas detector, soap and water, or equivalent
nonflammable solution, as applicable.
CAUTION: Since some leak test solutions, including soap and
water, may cause corrosion or stress cracking, the piping shall be rinsed with
water after testing, unless it has been determined the leak test solution is
noncorrosive.
(3) When
leakage or other defects are located, the affected portion of the piping system
shall be repaired or replaced and retested.
(4) Before gas is introduced into a system of
new gas piping, or back into an existing system after being shut off for
repair, the entire system shall be checked to determine that there are no open
fittings or ends and that all manual valves at outlets on equipment are closed
and all unused valves at outlets are closed and plugged or capped. Immediately
after turning on the gas, the piping system shall be checked to ascertain that
no gas is escaping If leakage is indicated, the gas supply shall be shut off
until the necessary repairs have been made.
(5) Dealers shall then forward to the board,
on an approved type form not later than the 15th of each month, a Report of
Installation covering each container and system installed and/or tested during
the preceding month. Additionally, the dealer shall provide the customer with a
copy of the Report for Installation.
S. In searching for leaks, soap suds,
peppermint, or other approved methods shall be used. The use of a flame for
searching leaks is prohibited.
T.
The pressure gauge used for testing the piping shall be graduated at intervals
not exceeding two (2) pounds, with a maximum overall graduation of not more
than 0 to 60 pounds.
U. Layout of
piping shall be in such manner as to insure its being run as directly as
possible, and shall be installed in a safe manner and in conformity with
generally accepted liquefied petroleum gas piping practice.
V. All piping installation shall have
provisions for expansion, contraction, vibration, and for settling to insure
that the system remains gas tight.
W. No piping should be run or concealed in
walls, partitions, etc. However, where the construction details of a building
or structure render this impractical, approval may be granted, providing the
piping has been tested under an air pressure of not less than 25 PSIG for a
period of not less than thirty (30) minutes. The test must be witnessed by the
owner, or user or a representative thereof, and a Report of Installation
forwarded in accordance with Section 9, Par. A. All piping must be wrought iron
or steel (either black or galvanized). The use of brass or copper pipe or
seamless copper or other non-ferrous metal tubing is prohibited unless
installed in approved type wrought iron or steel pipe chases or metal conduit.
In the event an addition to the unit is made after the initial test or any
alteration added it shall be tested in compliance with this requirement.
(1) When installing gas piping that is to be
concealed unions, tubing fittings, running threads, right and left couplings,
bushings, swing joints, and compression couplings made by combinations of
fittings shall not be used. Exception No. 1: Tubing joints shall either be made
with approved gas tubing fittings or be brazed with a material having a melting
point in excess of 1000 °F (538 C). Brazing alloys shall not contain more
than 0.05 percent phosphorus. Exception No. 2: Fittings listed for use in
concealed spaces that have been demonstrated to sustain, without leakage, any
forces due to temperature expansion or contraction, vibration or fatigue based
on their geographic location, application, or operation shall be permitted to
be used.
X. No piping or
tubing for use with liquefied petroleum gases shall be installed in concrete,
and where installed below concrete floors (prohibited for public buildings. see
Par. G.) there shall be a minimum covering of six (6) inches of sand or earth
between the top of the piping and the bottom of the concrete. It is recommended
where piping is installed below concrete floors, that it be adequately painted
or wrapped as a preventative against corrosion.
Y. Where a riser or piping enters a room
through a concrete floor it shall enter through a metal or other type conduit
slightly larger in diameter than the piping itself; or the piping shall be
painted and wrapped with a soft, resilient material of not less than one-eighth
(1/8) inch in thickness where in contact with the concrete.
Z. No piping shall be installed across any
floor where subject to being molested or stepped on, but shall be run along,
and adequately supported to, wall baseboard near floor level.
AA. All pipe and fittings to be welded must
be of the weldable type. The welding or brazing of any malleable fitting is
prohibited.
BB. The welding of any
liquefied petroleum gas pipe or fitting shall be performed by a certified
welder, or one approved by a representative of the Board.
CC. The use of aluminum tubing in exterior
locations, or where it is in contact with masonry or plaster walls or
insulation, is prohibited.
DD.
Horizontal runs of piping shall be supported by hangers in accordance with the
following tables: SIZE OF PIPE SPACING OF SUPPORTS 1/2 inch and smaller 6 feet
3/4 inch to 1 inch 8 feet 1 '/a inch and larger 10 feet
EE. Branch lines shall be installed so as to
come out of side or top of running lines, and not from the bottom.
FF. Where risers are placed outside of
building walls, they shall not be more than four (4) inches from such wall,
unless protected by a substantial post to prevent mechanical injury, and shall
be insulated where Butane or Butane-Propane mixture is used. No insulation is
required where straight Propane is used. The piping shall be coated with two
(2) coats of asphalt base paint, or other type inhibitor or preservative prior
to applying the insulation.
GG. No
person, firm, or corporation shall connect a liquefied petroleum gas container
to any piping installation without having first determined that all visible
piping of such installation complies with the rules and regulations of the
Liquefied Petroleum Gas Board as contained in the latest edition of the State
Code relative to liquefied petroleum gas piping.
H.H. LP Gas Containers Out of Service. When
the board receives a complaint concerning an out of service container, the
board or its director will notify the permit holder that it must retrieve the
container and corresponding equipment within thirty (30) days from initial
receipt of notification. Notification will be made by phone and both regular
and certified U.S. Mail. Permit holders who fail to retrieve the container and
equipment within thirty (30) days of receipt of notification will be fined
fifty dollars ($50.00) per day fine for each day beyond the thirty-day (30)
period, until the container and equipment are retrieved and may be subject to
injunctive action to have the container and equipment