6 CCR 1007-3-265.1060 - Standards: Closed-vent systems and control devices
(a) Owners or operators of closed-vent
systems and control devices subject to this subpart shall comply with the
provisions of ยง 265.1033 of this part.
(b)
(1) The
owner or operator of an existing facility who can not install a closed-vent
system and control device to comply with the provisions of this subpart on the
effective date that the facility becomes subject to the provisions of this
subpart must prepare an implementation schedule that includes dates by which
the closed-vent system and control device will be installed and in operation.
The controls must be installed as soon as possible, but the implementation
schedule may allow up to 30 months after the effective date that the facility
becomes subject to this subpart for installation and startup.
(2) Any units that begin operation after
December 21, 1990, and are subject to the provisions of this subpart when
operation begins, must comply with the rules immediately (i.e., must have
control devices installed and operating on startup of the affected unit); the
30-month implementation schedule does not apply.
(3) The owner or operator of any facility in
existence on the effective date of a statutory or EPA regulatory amendment that
renders the facility subject to this subpart shall comply with all requirements
of this subpart as soon as practicable but no later than 30 months after the
amendment's effective date. When control equipment required by this subpart can
not be installed and begin operation by the effective date of the amendment,
the facility owner or operator shall prepare an implementation schedule that
includes the following information: Specific calendar dates for award of
contracts or issuance of purchase orders for the control equipment, initiation
of on-site installation of the control equipment, completion of the control
equipment installation, and performance of any testing to demonstrate that the
installed equipment meets the applicable standards of this subpart. The owner
or operator shall enter the implementation schedule in the operating record or
in a permanent, readily available file located at the facility.
(4) Owners and operators of facilities and
units that become newly subject to the requirements of this subpart after
December 8, 1997 due to an action other than those described in paragraph
(b)(3) of this section must comply with all applicable requirements immediately
(i.e., must have control devices installed and operating on the date the
facility or unit becomes subject to this subpart; the 30-month implementation
schedule does not apply).
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.