(1) Application and scope. The purpose of
this rule is to establish a uniform procedure by which investor-owned electric
utilities calculate amounts due as contributions-in-aid-of-construction (CIAC)
from customers who request new facilities or upgraded facilities in order to
receive electric service, except as provided in Rule
25-6.078, F.A.C.
(2) Contributions-in-aid-of-construction for
new or upgraded overhead facilities (CIAC
OH) shall be
calculated as follows:
|
CIACOH
|
=
|
Total estimated work order job cost of installing
the facilities
|
-
|
Four years expected
incremental base energy
revenue
|
-
|
Four years expected incremental base demand
revenue, if applicable
|
(a) The cost
of the service drop and meter shall be excluded from the total estimated work
order job cost for new overhead facilities.
(b) The net book value and cost of removal,
net of the salvage value, for existing facilities shall be included in the
total estimated work order job cost for upgrades to those existing
facilities.
(c) The expected annual
base energy and demand charge revenues shall be estimated for a period ending
not more than 5 years after the new or upgraded facilities are placed in
service.
(d) In no instance shall
the CIACOH be less than zero.
(3) Contributions-in-aid-of-construction for
new or upgraded underground facilities (CIAC
UG) shall be
calculated as follows:
|
CIACUG
|
=
|
CIACOH
|
+
|
Estimated difference between cost of providing the
service underground and overhead
|
(4)
Each utility shall apply the formula in subsections (2) and (3) of this rule
uniformly to residential, commercial and industrial customers requesting new or
upgraded facilities at any voltage level.
(5) The costs applied to the formula in
subsections (2) and (3) shall be based on the requirements of Rule
25-6.030, F.A.C., Storm
Protection Plan, Rule
25-6.034, F.A.C., Standard of
Construction, Rule
25-6.0341, F.A.C., Location of
the Utility's Electric Distribution Facilities, and Rule
25-6.0345, F.A.C., Safety
Standards for Construction of New Transmission and Distribution
Facilities.
(6) All CIAC
calculations under this rule shall be based on estimated work order job costs.
In addition, each utility shall use its best judgment in estimating the total
amount of annual revenues which the new or upgraded facilities are expected to
produce.
(a) A customer may request a review
of any CIAC charge within 12 months following the in-service date of the new or
upgraded facilities. Upon request, the utility shall true-up the CIAC to
reflect the actual costs of construction and actual base revenues received at
the time the request is made.
(b)
In cases where more customers than the initial applicant are expected to be
served by the new or upgraded facilities, the utility shall prorate the total
CIAC over the number of end-use customers expected to be served by the new or
upgraded facilities within a period not to exceed 3 years, commencing with the
in-service date of the new or upgraded facilities. The utility may require a
payment equal to the full amount of the CIAC from the initial customer. For the
3-year period following the in-service date, the utility shall collect from
those customers a prorated share of the original CIAC amount, and credit that
to the initial customer who paid the CIAC. The utility shall file a tariff
outlining its policy for the proration of CIAC.
(7) The utility may elect to waive all or any
portion of the CIAC for customers, even when a CIAC is found to be applicable.
If however, the utility waives a CIAC, the utility shall reduce net plant in
service as though the CIAC had been collected, unless the Commission determines
that there is a quantifiable benefit to the general body of ratepayers
commensurate with the waived CIAC. Each utility shall maintain records of
amounts waived and any subsequent changes that served to offset the
CIAC.
(8) A detailed statement of
its standard facilities extension and upgrade policies shall be filed by each
utility as part of its tariffs. The tariffs shall have uniform application and
shall be nondiscriminatory.
(9) If
a utility and applicant are unable to agree on the CIAC amount, either party
may appeal to the Commission for a review.