Fla. Admin. Code Ann. R. 40C-3.461 - Inspection
(1) The District is authorized to inspect any
well or abandoned well within its jurisdiction, including those wells permitted
under Rule 40C-3.041, F.A.C. Inspections
shall be done as necessary to insure conformity with applicable standards. Such
inspection may include but need not be limited to geophysical logging, water
level measurements, or other methods. Duly authorized representatives of the
District, upon presenting proper identification and at reasonable times, may
enter upon any premises for the purpose of such inspection.
(2) If, based upon such inspection, the
District finds that the standards of Part II have not been met, the District
shall proceed with enforcement actions as prescribed by Chapter 62-531, F.A.C.,
which is incorporated by reference in subsection
40C-3.036(1),
F.A.C.
(3) A metallic tag shall be
placed on the well head, concrete marker, terminal box, or a permanently
attached fixture. The tag shall include, but not be limited to, the following
information:
(a) Contractor license
number,
(b) Date of
completion,
(c) Permit number
issued by the District.
1.
a. When a contractor provides tags a sample
copy of the tag must first be submitted to the District for approval.
b. Tags provided by the contractor must be
set in place at the time the well is completed.
2.
a. The
contractor may elect to use a metallic tag supplied by the District. Written
request may be made for such tag either on the permit application form or the
completion report, when filed. A fee of $5.00 per tag will be charged to cover
processing costs.
b. The contractor
shall certify on the completion report that the metallic tag will be placed
within 30 days of receipt by the contractor if using a district supplied tag as
set forth in this section.
(4) A site inspection will be conducted by an
authorized representative of the District prior to issuing a permit for
construction of a public water supply well.
(5) The District shall be notified at least
24 hours in advance of commencement of drilling operations and of placement of
grout in the annular space of any public supply water well. A District
representative will be on site to observe the commencement of drilling and
grouting. If the District is properly notified and an inspector is not at the
site at the appointed time or times, the commencement of drilling or grouting
may begin in the absence of a District representative. In all circumstances, a
copy of all applicable District permits will be available at the construction
site during installation.
(6) If,
based on an inspection, the District finds any well is an abandoned water well,
the well shall be plugged in accordance with Rule
40C-3.531, F.A.C.
(7) The District shall have the right to
inspect drilling records upon reasonable notice to a licensed
contractor.
Notes
Rulemaking Authority 373.044, 373.171 FS. Law Implemented 373.103, 373.308, 373.309, 373.319 FS.
New 10-14-84, Amended 12-5-85, Formerly 40C-3.461, 40C-3.0461, Amended 9-17-89, 7-27-16.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.