Fla. Admin. Code Ann. R. 40D-3.051 - Exemptions
(1) The following wells are exempt from the
requirements of Rule 40D-3.041, F.A.C.:
(a) Wells exempted under Section
373.303(7),
F.S.
(b) Wells used for the purpose
of temporary dewatering of subsurface formations for construction, mining or
quarrying purposes for a period of less than 6 months.
(c) Wells two inches or less in diameter and
less than 20 feet in depth used for no more than ten days for the purpose of
obtaining shallow soil or water information.
(2) In emergency situations when compliance
with the requirements of Chapter 373, Part III, F.S., or Chapter 40D-3, F.A.C.,
will result in undue hardship, incluing those situations when an unexpected
problem is encountered during the construction, repair or abandonment of a
well, the Executive Director, or the Executive Director's deignee, shall
authorize an exemption, by telephone, from the conditions required by a permit
or rule requirements for a well. A Well Completion Report documenting the
exemption must be submitted to the District in writing within 30 days of
completion.
(3) Qualifying for one
of the above exemptions does not relieve the applicant from obtaining any other
applicable permits required by law or District rule.
Notes
Rulemaking Authority 373.044, 373.113, 373.171, 373.309, 373.337 FS. Law Implemented 373.306, 373.308, 373.309, 373.313, 373.316, 373.326 FS.
New 10-5-74, Formerly 16J-3.13, Amended 7-1-90, 9-30-91, 12-31-92, 8-24-99.