The words, terms and phrases used in Chapter 62-17, F.A.C.,
unless otherwise indicated, shall have the meaning set forth in section
403.503, F.S. In addition, the
following words when used in Chapter 62-17, F.A.C., shall have the indicated
meanings:
(1) "Clerk of the Siting
Board" means the person designated as the clerk of the department pursuant to
Section 403.504(10),
F.S.
(2) "Construction" means any
clearing of land, excavation or other action which would alter the physical
environment or ecology of the site, but does not include those activities
essential for surveying, preliminary site evaluation or environmental
studies.
(3) "Electronic Copies"
means documentation submitted by the applicant which is stored on electronic
media (for example, compact disc) in a manner suitable for ease of copying and
pasting text or graphics into word processing software. Acceptable formats for
electronic copies include Microsoft Word for Windows Versions 5.0 or higher;
Rich Text Format, and portable document format (.pdf). Any portable document
format (.pdf) files must be of a version that all narrative and tables can be
readily converted to text.
(4)
"Expansion" means any increase in maximum steam or solar gross electrical
generating capacity of electrical power plants existing in 1973 as defined by
Section 403.506(1),
F.S.
(5) "Filing" means actual
receipt by the department's Siting Coordination Office, unless otherwise
specified herein.
(6)
"Postcertification amendment" means a material change in the information
provided in the application, by the licensee as certified, that does not
require a modification to the conditions of certification.
(7) "Precertification amendment" means any
amendment to the application made prior to certification. It does not include
information supplied by the applicant to make the application
complete.
(8) "Public notice" means
the notices required by Rule
62-17.281, F.A.C.
(9) "Secretary" means the Secretary of the
Department of Environmental Protection.
(10) "Supplemental Application" means an
application for certification for the construction and operation of an
additional steam or solar electrical power plant and associated facilities to
be located at a site which has been previously certified for an ultimate site
capacity.
Notes
Fla. Admin.
Code Ann. R. 62-17.021
Rulemaking Authority 403.504(1), 403.517(1) FS. Law
Implemented 403.503, 403.504(1), 403.5115, 403.517
FS.
New 5-7-74, Amended
12-27-77, Formerly 17-17.02, Amended 5-9-83, Formerly 17-17.021, Amended
2-1-99, 2-13-08, Amended by
Florida
Register Volume 47, Number 056, March 23, 2021 effective
4/8/2021.
New 5-7-74, Amended 12-27-77, Formerly 17-17.02, Amended
5-9-83, Formerly 17-17.021, Amended 2-1-99, 2-13-08,
4-8-21.