Fla. Admin. Code Ann. R. 62-17.660 - Post-Certification Monitoring and Reporting
(1) At its own expense, the licensee shall
conduct such postcertification monitoring and reporting required by the final
order of certification of the effects arising from the location of the
transmission line corridor, the construction of the transmission line or lines
and the maintenance of the transmission line right-of-way pursuant to the
conditions to assure continued compliance with the terms of certification. The
monitoring and reporting shall be carried out in the manner prescribed in the
conditions of certification established under Section
403.529(4),
F.S. and this rule.
(2) Within 90
days after certification, the licensee shall provide a complete summary of
those submittals where due dates are identified in the Conditions of
Certification. Such submittals include monitoring reports, management plans,
and wildlife surveys. The summary shall be provided to the Siting Coordination
Office and any affected agency to which the submittal is required to be
provided, in both electronic and paper form, using a sortable spreadsheet in a
format substantially similar to the following.
|
Condition number |
Requirement |
Due date or timeframe |
Name of agency to which the submittal is required to be provided |
Notes
Rulemaking Authority 403.532(1) FS. Law Implemented 403.523(10) FS.
New 11-20-80, Amended 6-26-84, Formerly 17-17.66, 17-17.660, Amended 5-24-10.