(1) This general permit authorizes the
following activities:
(a) The repair,
rehabilitation, or replacement of any previously authorized, currently
serviceable structure or fill, or of any currently serviceable structure or
fill authorized by 33 CFR
§
330.3 as of July 1, 2019, incorporated
by reference herein (
https://www.flrules.org/Gateway/reference.asp?No=Ref-12074),
provided that the structure or fill is not to be put to uses differing from
those uses specified or contemplated for it in the original permit or the most
recently authorized modification. Minor deviations in the structure's
configuration or filled area, including those due to changes in materials,
construction techniques, requirements of other regulatory agencies, or current
construction codes or safety standards that are necessary to make the repair,
rehabilitation, or replacement are authorized.
(b) The removal of previously authorized
structures or fills. Any stream channel modification is limited to the minimum
necessary for the repair, rehabilitation, or replacement of the structure or
fill; such modifications, including the removal of material from the stream
channel, must be immediately adjacent to the project.
(c) The removal of accumulated sediment and
debris within, and in the immediate vicinity of, the structure or
fill.
(d) The repair,
rehabilitation, or replacement of those structures or fills destroyed or
damaged by storms, floods, fire or other discrete events, provided the repair,
rehabilitation, or replacement is commenced, or is under contract to commence,
within two years of the date of their destruction or damage. In cases of
catastrophic events, such as hurricanes or tornadoes, this two-year limit may
be waived by the Agency, provided the permittee can demonstrate funding,
contract, or other similar delays.
(e) The removal of accumulated sediments and
debris outside the immediate vicinity of existing structures (e.g., bridges,
culverted road crossings, water intake structures, etc.). The removal of
sediment is limited to the minimum necessary to restore the waterway in the
vicinity of the structure to the approximate dimensions that existed when the
structure was built but cannot extend farther than 200 feet in any direction
from the structure. This 200-foot limit does not apply to maintenance dredging
to remove accumulated sediments blocking or restricting outfall and intake
structures. All dredged or excavated materials must be deposited and retained
in an area that has no state-assumed waters unless otherwise specifically
approved by the Agency under separate authorization.
(f) Temporary structures, fills, and work,
including the use of temporary mats, necessary to conduct the maintenance
activity. Appropriate measures must be taken to maintain normal downstream
flows and minimize flooding to the maximum extent practicable, when temporary
structures, work, and fill, including cofferdams, are necessary for
construction activities, access fills, or dewatering of construction sites.
Temporary fills must consist of materials, and be placed in a manner, that will
not be eroded by expected high flows. After conducting the maintenance
activity, temporary fills must be removed in their entirety and the affected
areas returned to pre-construction elevations. The areas affected by temporary
fills must be revegetated.
(3) Notice of intent to use this general
permit is required for activities authorized by paragraph (1)(e). The notice
must include information regarding the original design capacities and
configurations of the outfalls, intakes, and small impoundments.
Editor notes:
The effective date of the
rule will be the effective date of assumption, which is the date identified by
EPA as published in the Federal Register §
373.4146,
F.S.