Except as allowed under subsection
62-555.340(5),
F.A.C., or by special permit condition established in accordance with paragraph
62-555.533(2)(f),
F.A.C., no public water system (PWS) components constructed or altered under a
permit granted by the Department shall be placed into permanent operation
without prior Department approval, or clearance, as described below.
(1) Upon completing, or substantially
completing, the construction of new or altered PWS components, and before
placing the components into operation for any purpose other than disinfection,
testing for leaks, or testing equipment operation, the permittee shall submit
to the appropriate Department of Environmental Protection (DEP) District Office
or Approved County Health Department one copy of a completed certification of
construction completion using Form
62-555.900(9),
Certification of Construction Completion and Request for Clearance to Place
Permitted PWS Components into Operation, hereby adopted and incorporated by
reference, effective August 28, 2003. Copies of this form are available from
the Department of Environmental Protection, Drinking Water Section, M.S. 3520,
2600 Blair Stone Road, Tallahassee, Florida 32399-2400. This certification
shall be accompanied by one copy of the following information:
(a) The portion of record drawings showing
deviations from the DEP construction permit, including the approved preliminary
design report or drawings and specifications, if there are any deviations from
said permit. (Note that it is necessary to submit a copy of only the portion of
record drawings showing deviations and not a complete set of record
drawings.)
(b) Bacteriological test
results, including a sketch or description of all bacteriological sampling
locations, demonstrating compliance with subsection
62-555.315(6),
or Rule
62-555.340, F.A.C., if any of
the new or altered PWS components must be disinfected and bacteriologically
surveyed or evaluated per said subsection or said rule.
(c) Analytical test results demonstrating
compliance with Part III of Chapter 62-550, or subsection
62-524.650(2),
F.A.C., if any of the new or altered PWS components are necessary to achieve,
or affect, compliance with said part or said subsection.
(d) A completed Form
62-555.900(20),
New Water System Capacity Development Financial and Managerial Operations Plan,
as incorporated into Rule
62-555.357, F.A.C., if the new
or altered PWS components were constructed under a permit issued by the
Department before the effective date of Rule
62-555.525, F.A.C., (9-22-99)
and create a "new system" as described under subsection
62-555.525(1),
F.A.C.
(e) Any other information
required by conditions in the DEP construction permit.
(2) Within 14 days after receiving a
certification of construction completion for PWS components constructed or
altered under a general permit, the Department shall review the certification.
If the Department finds anything that will prevent the new or altered
components from functioning in compliance with Chapters 62-550 and 62-555,
F.A.C., or if the Department finds that the new or altered components will
cause, or contribute to, a PWS's noncompliance with Chapter 62-550 or 62-555,
F.A.C., the Department shall issue to the permittee, within the aforementioned
14-day review period, a written request for corrective action and for
resubmittal of the certification after the corrective action is
completed.
(3) Within 30 days after
receiving a certification of construction completion for PWS components
constructed or altered under a specific permit, the Department shall review the
certification and, if the new or altered components create a "new system" as
described under subsection
62-555.525(1),
F.A.C., shall inspect the "new system." If the Department finds anything that
will prevent the new or altered components from functioning in compliance with
Chapters 62-550 and 62-555, F.A.C., if the Department finds anything that will
prevent a "new system" from functioning in compliance with Chapters 62-550,
62-555, 62-560, and 62-699, F.A.C., or if the Department finds that the new or
altered components will cause, or contribute to, an existing PWS's
noncompliance with Chapter 62-550 or 62-555, F.A.C., the Department shall issue
to the permittee, within the aforementioned 30-day review/inspection period, a
written request for corrective action and for resubmittal of the certification
after the corrective action is completed.
(4) Within 14 days after receiving a
satisfactory certification of construction completion for PWS components
constructed or altered under a general permit and within 30 days after
receiving a satisfactory certification of construction completion for PWS
components constructed or altered under a specific permit, the Department shall
issue written approval, or clearance, to place the new or altered components
into permanent operation. The Department shall issue the clearance to the
permittee and shall provide a copy of the clearance to the PWS supplying water
to the new or altered components if said PWS is not the permittee.
(5) Suppliers of water shall ensure that
permittees have obtained written clearance from the Department before suppliers
of water turn on water service to permittees.