Fla. Admin. Code Ann. R. 62-807.580 - Postcertification - Easements
(1) Where the
certification is issued requiring approval for easement or other interest in
state lands, the title to which is vested in the Board of Trustees of the
Internal Improvement Trust Fund (Trustees), the licensee must apply directly to
the Trustees for each required easement or other interest in state lands for
such approval. Likewise, the licensee must apply to the appropriate water
management district (WMD) for easement-approval for lands for which the title
is vested in a WMD created pursuant to Chapter 373, F.S. The licensee must
forward the easement approval request to the Department. The Trustees or WMD,
or the licensee if the Trustees or WMD fails to do so, must forward the letter
of approval for such easement or other interest to the Department so that the
Department can verify compliance with the conditions of
certification.
(2) An applicant may
apply to the Trustees or a WMD for an easement or other interest in land either
before or after filing an application for the certification of a pipeline
corridor. Such application may also be sought during the certification
proceedings. The Trustees or WMD may condition any easement or other
authorization to use lands granted prior to certification to require
certification before the authorized use is commenced.
Notes
Rulemaking Authority 403.9404(1) FS. Law Implemented 403.9416(3) FS.
New 8-12-93, Formerly 17-807.580, Amended 3-3-15.