Fla. Admin. Code Ann. R. 62-814.310 - Deviations from Standards and Criteria
(1) Deviations from the standards and
criteria contained in publications listed in subsection
62-814.300(2),
F.A.C., above or equivalent methodology for the computation and measurement
methodology referenced in rule
62-814.460, F.A.C., may be
approved by the Department provided the applicant's engineer's report provides
reasonable assurance that the proposed design, calculations or measurement
methods will result in electrical facilities meeting the requirements of this
rule.
(2) The Department may
approve deviations from the standards and criteria contained in the
publications listed in subsection
62-814.300(2),
F.A.C., above or equivalent methodology for the computation or measurement of
electric and magnetic fields upon a finding that conformance to them will not
result in noncompliance with the remainder of this chapter or other rules of
this Department in accordance with the following:
(a) The owner or operator of any electrical
facility subject to the provisions of this section may request in writing a
determination by the Secretary or the Secretary's designee that any requirement
of rule 62-814.300 or
62-814.460, F.A.C., relating to
measurement or calculation of electric or magnetic fields, procedures, test
equipment, methodology, or test facilities shall not apply to such electrical
facility, and shall request approval of alternate standards or
criteria.
(b) The request shall set
forth the following information, at a minimum:
1. Specific electrical facility for which an
exception is required.
2. The
specific provision(s) of rule
62-814.300 or
62-814.460, F.A.C., from which
an exception is sought.
3. The
basis for the exception, including but not limited to any hardship which would
result from compliance with the provisions of rule
62-814.300 or
62-814.460, F.A.C.
4. The alternate standard(s) or criteria for
which approval is sought and a demonstration that such alternate standard(s) or
criteria shall be adequate to demonstrate compliance with the field strength
standards contained in this chapter.
(c) The Secretary or the Secretary's designee
shall specify by order each alternate standard or criteria approved for an
individual electrical facility in accordance with this section or shall issue
an order denying the request for approval. The Department's order shall be the
final agency action, reviewable in accordance with section
120.57,
F.S.
Notes
Rulemaking Authority 403.061(7), 403.523(1) FS. Law Implemented 403.061(31), 403.523(14) FS.
New 3-21-89, Amended 1-7-93, Formerly 17-274.301, 17-814.310.