Fla. Admin. Code Ann. R. 62B-56.090 - Financial Assurances
(1) Prior to
issuance of a Notice to Proceed, the responsible entity shall provide the
Department with financial assurance, as defined in rule
62B-56.020, F.A.C., in an amount
sufficient to cover the cost of dune core removal and restoration of the
project site, including topography and native beach-dune vegetation, and a
one-time deferred removal cost, as defined in rule
62B-56.020, F.A.C. In the event
the responsible entity fails to remove and restore pursuant to rule
62B-56.160, F.A.C., the
financial assurance shall be used to conduct such removal and
restoration.
(2) Proof of financial
assurance shall be submitted on either Form
62B-56.900(10)"Trust
Fund Agreement" (effective date 6-22-09); Form
62B-56.900(11),
"Payment Bond" (effective date 6-22-09); Form
62B-56.900(12),
"Performance Bond" (effective date 6-22-09); Form
62B-56.900(13),
"Letter of Credit" (effective date 6-22-09); or, Form
62B-56.900(14)"Standby
Trust Agreement" (effective date 6-22-09), as appropriate. These forms are
incorporated by reference. Copies of forms may be obtained by writing to the
Department of Environmental Protection, 2600 Blairstone Road, MS 3522,
Tallahassee, Florida 32399-2400; or at the following website:
www.dep.state.fl.us/beaches. A
standby trust agreement must accompany any surety payment bond or performance
bond or letter of credit.
(3) The
amount of the financial assurance shall be based on a cost estimate provided by
an individual qualified to make such an estimate who is not the applicant or an
employee of the applicant, or associated with the sale, installation, or
contract for removal, of the geotextile container to be permitted under this
chapter. The individual providing the estimate may be a professional engineer
or general contractor licensed in the State of Florida or other person who has
demonstrated similar qualifications to the Department. The estimate shall
include the costs associated with removal of the geotextile container and
restoration of the project site, including topography and native beach-dune
vegetation, and the cost of a one-time deferred removal, consistent with
subsection 62B-56.160(6),
F.A.C., and based on the engineering documents submitted with the application.
The costs shall be estimated on a per unit basis, with the description of the
estimates indicated, and shall be submitted on Form
62B-56.900(2),
"Financial Assurance Worksheet" (effective date 6-22-09), as part of the permit
application. This form is incorporated by reference. Copies of forms may be
obtained by writing to the Department of Environmental Protection, 2600
Blairstone Road, MS 3522, Tallahassee, Florida 32399-2400; or at the following
website: www.dep.state.fl.us/beaches.
(4) As part of the permit application, the
applicant must also submit a written commitment from the financial institution
or insurance company providing or acting as Trustee of the financial assurance
that such funds or instruments in the amount estimated on Form
62B-56.900(2),
"Financial Assurance Worksheet" (effective date 6-22-09), will be made
available to the responsible entity prior to the issuance of the Notice to
Proceed. This form is incorporated by reference. Copies of forms may be
obtained by writing to the Department of Environmental Protection, 2600
Blairstone Road, MS 3522, Tallahassee, Florida 32399-2400; or at the following
website: www.dep.state.fl.us/beaches.
(5) The responsible entity shall revise and
resubmit the cost estimate, Form
62B-56.900(2),
"Financial Assurance Worksheet" (effective date 6-22-09), every five years from
the date of permit issuance to adjust for inflation or other changes in costs,
and shall provide the revised financial assurance to the Department. This form
is incorporated by reference. Copies of forms may be obtained by writing to the
Department of Environmental Protection, 2600 Blairstone Road, MS 3522,
Tallahassee, Florida 32399-2400; or at the following website:
www.dep.state.fl.us/beaches.
(6) Prior to any transfer of the permit, the
new responsible entity (transferee) must provide the Department with proof of
financial assurance to cover the cost of dune core removal and restoration of
the project site, including topography and native beach-dune vegetation, and
the one-time deferred removal cost. The new responsible entity's (transferee's)
financial assurance may be satisfied by proof of the continuation of the
existing financial assurance.
Notes
Rulemaking Authority 161.053(20), 161.085(5) FS. Law Implemented 161.053(4), 161.085(9) FS.
New 6-22-09.