Fla. Admin. Code Ann. R. 66B-2.004 - Policy
The following constitutes the policy of the District regarding the administration of the program:
(1) Financial Assistance Eligibility:
Financial assistance, support and cooperation may be provided to eligible
governmental agencies for approved projects as follows:
(a) Member counties may be provided financial
assistance, support or cooperation in planning, acquisition, development,
construction, reconstruction, extension, improvement, operation or the
maintenance of public navigation, local and regional anchorage management,
beach renourishment, public recreation, inlet management, environmental
education, maritime management plans, and boating safety projects directly
related to the waterways.
(b)
Eligible local governments may also be provided financial assistance, support
and cooperation in planning and carrying out public navigation, local and
regional anchorage management, beach renourishment, public recreation, inlet
management, environmental education, and boating safety projects directly
related to the waterways.
(c)
Navigation related districts may be provided with financial assistance to pay
part of the costs of the planning and acquisition of dredge material management
sites if the Board finds that the site is required for the long-range
maintenance of the Atlantic Intracoastal Waterway channel. All such sites must
meet the development and operational criteria established by the District
through a long-range dredge material management plan for that county.
Navigation related districts may also be provided with assistance for waterway
related access projects, environmental mitigation projects associated with
waterway improvement related activities, and inlet management projects if the
Board finds that the project benefits public navigation in the Atlantic
Intracoastal Waterway. All navigation related districts shall contribute at
least equal matching funds to any District financial assistance provided.
Seaports may also be furnished assistance and support in planning and carrying
out environmental mitigation projects. All seaport projects shall benefit
publicly maintained channels and harbors. Each seaport shall contribute
matching funds for funded projects.
(d) Eligible projects shall include the
acquisition and development of public boat ramps and launching facilities,
including those in man-made, navigable waterways contiguous to "waterways" as
defined in Rule 66B-2.003, F.A.C.
(2) Notification: The District will notify by
direct mail, email and/or advertised public notice all eligible governmental
agencies of the program and the upcoming authorized submission
period.
(3) Project Approval:
Approval of projects by the District shall be in accordance with these
rules.
(4) Project Accessibility:
Facilities or programs funded in whole or in part by program funds shall be
made available to the general public of all of the member counties on a
non-exclusive basis without regard to race, color, religion, age, sex or
similar condition. Additionally, facilities funded in whole or in part by
program funds, shall not require a paid membership for the general public of
all of the member counties as a condition to use the facilities. User or
entrance fees may be charged for the use of facilities funded in whole or in
part by program funds, however such fees shall be reasonable and shall be the
same for the general public of all of the member counties.
(5) Waterway Impacts: All development
projects must be designed so as not to impact navigation along the District's
waterways through the placement of structures, attendant uses, or the necessity
of a boating speed zone for safety purposes. Before applying for boating speed
zone designation in District waterways because of a project funded by this
program, the sponsor shall first receive approval from the Board. The Board
will use the criteria found in Section 327.46(1), F.S., in determining whether
to approve the proposed boating speed zone.
(6) Project Maintenance: The project sponsor
shall be responsible for the operation, maintenance, and management of the
project for the anticipated life of the project and shall be responsible for
all expenses required for such purposes. The project shall be maintained in
accordance with the standards of maintenance for other similar local facilities
and in accordance with applicable health standards. Project facilities and
improvements shall be kept reasonably safe and in reasonable repair to prevent
undue deterioration and to encourage public use. The project sponsor shall have
full legal authority and financial ability to operate and maintain the project
facilities.
(7) Education
Facilities and Programs: Waterways related environmental education facilities
and programs sponsored by the District shall occur at specially designated
environmental education facilities located adjacent and contiguous to the
waterways. It is the District's intent to consolidate its environmental
education efforts in the least number of facilities within an area that will
adequately serve the education needs of that area of the District.
(8) Public Information Availability: Public
information produced with assistance from this program shall not be copyrighted
and shall be provided free of cost, except for the cost of reproduction, to the
public.
(9) Third-Party Project
Operators: Projects that are being operated by a third party shall have
sufficient oversight by the eligible project sponsor as determined by the
Board. Such oversight, at a minimum, will include a project liaison that is a
staff member of the eligible project sponsor, and oversight of the operating
hours and admission fees of the facility by the eligible project sponsor
through a legal agreement. All third party projects shall be open to the public
in accordance with this rule.
(10)
Non-compliance: The District shall terminate a project agreement and demand
return of program funds disbursed to the project sponsor for non-compliance
with any of the terms of the project agreement or this rule, if such
non-compliance calls into question the ability of the applicant to complete the
project. Failure of a project sponsor to comply with the provisions of this
rule or the project agreement shall result in the District declaring the
project sponsor ineligible for further participation in the program until such
time as compliance has been met to the satisfaction of the District.
(11) Fees: Any public project eligible for
District program funds that charges a fee or will charge a fee must create and
maintain an enterprise fund for the public project that shall plan for and
retain at all times sufficient funds for the on-going maintenance of the
facility during its project life. Accounting records of the previous five years
of the public project's enterprise fund will be submitted as part of any
subsequent assistance program application to the District.
Notes
Rulemaking Authority 374.976(2) FS. Law Implemented 374.976(1), (2) FS.
New 12-17-90, Amended 2-3-94, 2-6-97, Formerly 16T-2.004, Amended 5-18-98, 3-31-99, 5-25-00, 3-21-01, 7-30-02, 3-3-04, 4-21-05, 4-1-09, 2-22-10, 3-7-11, 3-7-12, 1-27-14, 2-17-15.