Ga. Comp. R. & Regs. R. 391-3-20-.08 - Quality Control and Equipment Calibration Procedures
(1) All Georgia Analyzer Systems (GAS) shall,
at a minimum, be calibrated according to the procedures and schedules as
prompted by the GAS.
(2) No person
shall operate a GAS for the purpose of performing an emissions inspection
unless the Georgia Analyzer System:
(a) has
passed all calibrations, audits, and leak checks as prompted by the
GAS;
(b) in the case of a GAS that
is not a mobile GAS, is connected to the dedicated data transmission line as
described in
391-3-20-.09(2)(i);
and
(c) in the case of a GAS that
is a mobile GAS, is connected to the dedicated data transmission line within 72
hours of any inspection performed at a fleet or car dealer location and at all
times when the mobile GAS is located at the inspection station location
identified on the Certificate of Authorization.
(3) Any station or GAS that has not performed
an inspection in more than 90 days, shall not resume performing inspections
until the Management Contractor has been contacted and a passing audit has been
performed by the Management Contractor on the station's GAS(s).