Ga. Comp. R. & Regs. R. 391-3-23-.05 - Permit Amendment
(1)
If, during the course of construction, conditions arise which result in a
material or substantial change of any of the bases of the approved permit
(including, but not limited to, deviation from the original route that goes out
of the original easement or right of way, change of ownership, or new
information that impacts the environmental analysis) the applicant will submit
a request for a permit amendment describing the change and the reasons for the
change.
(2) After review and
determination that sufficient information exists to justify that the amendment
is necessary and does not require a new permit application, the Director will
post for 30 days a notice of the draft amendment for public comment on the web
site. After close of the public comment period, the Director will grant or deny
the amendment.
(3) If the proposed
amendment results in additional landowners whose property will be located
within 1,000 feet of the proposed route the applicant shall comply with
provisions of
391-3-23-.03(5).