Ga. Comp. R. & Regs. R. 391-3-8-.05 - Application for a Permit
(1) No Person shall operate or construct a
dam as defined by the Act and these Rules without first having obtained a
permit from the Division; provided, however, any persons who is operating a dam
may continue such operation pending final action by the Director on the permit
application, and provided such application has been filed with the Director
within 180 days after that permit is required by the Director.
(2) Permit applications shall be on forms as
may be prescribed and furnished by the Division.
(3) The Director may require the submission
of plans, specifications, and other information as he deems relevant to the
application.
(4) If a permit
application for the construction of a dam is not approved by the Director, the
application shall be returned to the applicant along with the reasons for its
disapproval.
Such applicants may reapply for said permit by correcting deficiencies in the application and resubmitting the application to the Director.
(5) Permits shall
not be transferred from one person to another without the approval of the
Director. If the ownership changes from one person to another, the new owner
shall immediately notify the Director in writing of such transactions. The
Director shall also be notified of any proposed change in the operation of the
dam.
(6) Permits shall not be
transferred from one dam to another dam.