Ga. Comp. R. & Regs. R. 672-5-.10 - Certification of Capacity
(1) In order that the Department may have the
necessary information to pass upon the ability of a Prospective Bidder to
satisfactorily complete a project, each low bidder must submit on each proposal
within one (1) business day after the letting a Certification of Capacity to
perform the work. Such forms may be obtained from the office of the
Prequalification Committee. In making this certification, the Prospective
Bidder certifies that its Current Capacity is sufficient to cover the amount of
its proposal.
(2) If the
Prospective Bidder certifies that it has obligations of uncompleted work under
contract, the initiation of work on which for good and sufficient contractual
reasons, must be deferred beyond a period of twelve (12) months after the date
of the opening of bids for the work for which the Prospective Bidder is
submitting its bid, the Prequalification Committee may give consideration to
temporarily reducing the debits against the Prospective Bidder's Current
Capacity by the amounts of the dollar values of such items. If the Prospective
Bidder desires such consideration where the award of a contract is contingent
upon the deferral of such charges against its Current Capacity, Prospective
Bidder must list the projects on which such deferrals are requested in its
Certification of Capacity and it must attach a detailed explanation of the
circumstances.
(3) The penalty for
making a false Certification of Capacity may be disqualification from bidding
on future work for a ninety (90) day period. The appeal procedure will be the
same as that set out in
672-5-.14(2).