Ga. Comp. R. & Regs. R. 672-5-.12 - Effect of Subcontracting on Contractor's Capacity
(1) The prime Contractor may subcontract
portions of the project to other prequalified Contractors or registered
Subcontractors up to the amount provided for in the contract specifications. In
figuring the total amount of Current Capacity available to a Contractor, it
will be given credit for the work subcontracted after the Subcontractor has
been approved in writing by the Department.
(2) No Person shall both prequalify as a
Contractor and register as a Subcontractor. Any subcontract work undertaken by
a prequalified Contractor shall be counted against its Current
Capacity.