Haw. Code R. § 11-200.1-14 - Determination of level of environmental review
(a) Fcr an
agency action, through its judgment and experience, a proposing agency shall
assess the significance of the potential impacts of the action to determine the
level of environmental review necessary for the action.
(b) For an applicant action, within thirty
days from the receipt of the applicant's complete request for approval to the
approving agency, through its judgment and experience, an approving agency
shall assess the significance of the potential impacts of the action to
determine the level of environmental review necessary for the action.
(c) If the proposing agency or approving
agency determines, through its judgment and experience, that the action will
individually and cumulatively probably have minimal or no significant effects,
and the action is one that is eligible for exemption under subchapter
8, then the proposing agency or the
approving agency in the case of an applicant may prepare an exemption notice in
accordance with subchapter
8.
(d) If the proposing agency or approving
agency determines, through its judgment and experience that the action is not
eligible for an exemption, then the proposing agency shall prepare, or the
approving agency shall require the applicant to prepare, an EA beginning with a
draft EA in accordance with subchapter 9, unless:
(1) In the course of preparing the draft EA,
the proposing agency or approving agency determines, through its judgment and
experience that the action may have a significant effect and therefore require
preparation of an EIS, then the proposing agency may prepare, or the approving
agency may authorize the applicant to prepare, an EA as a final EA to support
the determination prior to preparing or requiring preparation of an EIS in
accordance with subchapter 10; or
(2) The proposing agency or approving agency
determines, through its judgment and experience that an EIS is likely to be
required, then the proposing agency may choose to prepare, or an approving
agency may authorize an applicant to prepare, an EIS in accordance with
subchapter 10, beginning with preparation of an EISPN.