Haw. Code R. § 11-23-08 - Construction conditions
(a) No injection
well shall be constructed unless, prior to the start of any construction:
(1) Application is made for a UIC permit and
all application procedures set forth in sections
11-23-12 through
11-23-15 are completed;
(2) It is shown that
the proposed injection well will comply with this chapter; and
(3) The department, upon satisfaction of the
reguirements set forth in paragraphs (1) and (2), approves the start of
construction.
(b)
Approval of the start of the construction of any injection well shall not be
construed as approval for the Operation of that injection well. Further, the
approval of the start of construction does not guarantee the approval to
operate upon completion of the injection well. Permits shall be issued only in
accordance with this chapter and it is the duty of the applicant to insure
compliance with the law and this chapter.