Haw. Code R. § 11-280.1-324 - Application for a permit
(a) Every
application for a permit shall be submitted to the department on the
"Application for an Underground Storage Tank Permit" form prescribed by the
director.
(b) A permit fee in
accordance with section
11-280.1-335 shall accompany each
application for a permit.
(c) The
applicant shall submit sufficient information to enable the director to make a
decision on the application. Information submitted shall include but not be
limited to the following:
(1) General
information on involved parties, including the landowner, UST owner, and UST
operator; location of the property (including TMK); and basic description of
the UST or tank system;
(2) Age,
size, precise location within the property, and use of each UST;
(3) Description of tanks, piping, ancillary
equipment, spill and overfill prevention equipment, and release detection
equipment;
(4) Other information
required in the form prescribed by the director; and
(5) Other information as the department may
require.
(d) Every
application shall be signed by the owner and the operator and shall constitute
an acknowledgment that the applicants assume responsibility for the
installation and operation of the UST or tank system in accordance with this
chapter and the conditions of the permit, if issued. Each signatory shall be:
(1) In the case of a corporation, a principal
executive officer of at least the level of vice president, or a duly authorized
representative if that representative is responsible for the overall operation
of the UST or tank system;
(2) In
the case of a partnership, a general partner;
(3) In the case of a sole proprietorship, the
proprietor; or
(4) In the case of a
county, state, or federal entity, either a principal executive officer, ranking
elected official, or other duly authorized employee.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
(a) Every application for a permit shall be submitted to the department on the "Application for an Underground Storage Tank Permit " form prescribed by the director .
(b) A permit fee in accordance with section 11-280.1-335 shall accompany each application for a permit .
(c) The applicant shall submit sufficient information to enable the director to make a decision on the application. Information submitted shall include but not be limited to the following:
(1) General information on involved parties, including the landowner, UST owner, and UST operator ; location of the property (including TMK); and basic description of the UST or tank system ;
(2) Age, size, precise location within the property, and use of each UST ;
(3) Other information required in the form prescribed by the director ; and
(4) Other information as the department may require.
(d) Every application shall be signed by the owner and the operator and shall constitute an acknowledgment that the applicants assume responsibility for the installation and operation of the UST or tank system in accordance with this chapter and the conditions of the permit , if issued. Each signatory shall be:
(1) In the case of a corporation, a principal executive officer of at least the level of vice president, or a duly authorized representative if that representative is responsible for the overall operation of the UST or tank system ;
(2) In the case of a partnership, a general partner;
(3) In the case of a sole proprietorship, the proprietor; or
(4) In the case of a county, state, or federal entity, either a principal executive officer, ranking elected official, or other duly authorized employee.