Haw. Code R. § 12-220-9.1 - Design, construction, fabrication installation, repair, or alteration of boiler external and non-boiler external piping
(a) Application for authorization for
installation of boiler external piping shall be submitted to the department
prior to the commencement of work. An application shall be submitted in the
form prescribed by the director and must be accompanied by the remittance of
the fee for each boiler external piping subject to this part as per the
schedule in Exhibit A, titled, "Installation, Repair or Alteration Permit Fees,
and Licensure, Examination, and Registration Fees", dated October 1, 2023,
which is made part of this chapter and located at the end of this chapter, and
inspection fee for each pressure retaining item subject to this part as per the
schedule in Exhibit B, titled, "Internal & External Inspection Fees", dated
October 1, 2023, which is made a part of this chapter and located at the end of
this chapter. A complete application shall include:
(1) Date of application, project name, and
address;
(2) Manufacturer's and
installer's name, address, and installer's type of license held along with the
expiration date;
(3) Contact person
and phone number for the owner, manufacturer, and installer;
(4) National Board number of the boiler where
the piping is to be installed;
(5)
Copy of the ASME manufacturer's data report and partial data reports;
(6) Floor plan layout with clearance
dimensions; and
(7) Piping and
instrumentation diagram.
(b) Application for authorization for design,
fabrication, installation, repair, or alteration of non-boiler external piping
shall be submitted by a holder of a valid ASME certificate of authorization
with "S", "A", or "PP" designator, a NB "R" authorization, or a NBEP Hawaii
certification of authorization, to the department prior to the commencement of
work. An application shall be submitted on a form provided by the department
and must be accompanied by the remittance of the fee for each non-boiler
external piping subject to this part as per the schedule in Exhibit A, titled,
"Installation, Repair or Alteration Permit Fees, and Licensure, Examination,
and Registration Fees", dated October 1, 2023, which is made part of this
chapter and located at the end of this chapter, and inspection fee for each
pressure retaining item subject to this part as per the schedule in Exhibit B,
titled, "Internal & External Inspection Fees", dated October 1, 2023, which
is made a part of this chapter and located at the end of this chapter. A
complete application shall include:
(1) Date
of application, project name, and address;
(2) Manufacturer's and installer's name,
address, and installer's type of license held along with the expiration
date;
(3) Contact person and phone
number for the owner, manufacturer, and installer;
(4) National Board number of the boiler where
the piping is to be installed;
(5)
Copy of the ASME manufacturer's data report;
(6) Floor plan layout with clearance
dimensions; and
(7) Piping and
instrumentation diagram.
(c) Repairs and alterations of NBEP shall be
in accordance with NBIC Part 3 and ASME B31.1 whenever applicable. Repair
inspector involvement may be waived, and stamping is not mandatory.