Haw. Code R. § 13-183-29 - Term of mining leases
(a) The term of all
mining leases shall consist of a primary ten-year period and continuation
periods which shall be as provided herein, except that the sum of primary and
all continuation periods of the leases shall not exceed sixty-five years from
the effective date of the initial lease. The effective date of all leases shall
be the first day of the month following the board's signing of the
lease.
(b) If during the primary
period of a mining lease, geothermal resources or by-products are being
produced or utilized in commercial quantities, that lease shall continue for so
long thereafter as geothermal resources or by-products are produced or utilized
in commercial quantities subject to the limitation of subsection (a) herein.
Production or utilization of geothermal resources in commercial quantities for
purposes of this subsection shall be deemed to include the completion of one or
more wells producing or capable of producing geothermal resources for delivery
to or utilization by a facility or facilities not yet installed but scheduled
for installation not later than fifteen years from the date of commencement of
the primary term of the lease.
(c)
If, at the end of the primary term of a mining lease, geothermal resources are
not being produced from the leased land, but the lessee is actively engaged in
drilling operations under said lease below the depth of 1,000 feet or at a
lesser depth of productive zone in a diligent manner, that lease may be
continued, at the discretion of the board, for a period of not more than five
years and for as long thereafter as geothermal resources are being produced or
utilized in commercial quantities subject to the sixty-five year limit provided
in subsection (a) herein.
(d) If
the board determines that the lessee has voluntarily shut in production for
lack of a market but is proceeding diligently to acquire a contract to sell or
to utilize the production or is progressing with installations needed for
production, the lease shall be continued in force for the duration of the
primary term or for five years after shut-in, whichever is longer, upon payment
of rentals, or the lease may be terminated by the board. The chairperson shall
continue to review shut-in leases at least once every five years until
production in commercial quantities occurs, the lease is terminated by the
board for lessee's lack of due diligence, or surrender by the lessee.
(e) If production of geothermal resources
under a lease ceases from any cause after expiration of the primary term or
before the end of the primary term if production has commenced, that lease
shall continue so long as the lessee actively and continuously engages in
drilling or reworking operations which shall be commenced within one hundred
eighty days after cessation of production. Continuous drilling of reworking
operations shall be deemed to have occurred if no more than one hundred eighty
days elapses between cessation of operations on one well and commencement of
operations on the same or another well. If the operations are successful, the
lease shall continue for so long thereafter as geothermal resources are
produced or utilized in commercial quantities, subject to subsection (a)
herein.
(f) If the lessee is
rendered unable wholly or in part by force majeure to carry out its obligations
under a lease, lessee shall give to lessor prompt written notice of the force
majeure. Any obligations of the lessee to perform so far as they are affected
by the force majeure shall be suspended during the continuance of the force
majeure and the primary term or any continuation period shall be extended for a
period equal to the period of suspended performance caused by the force
majeure. Lessee shall use all possible diligence to remove or correct the force
majeure; provided, however, that any cure shall not require the settlement of
strikes, lockouts or other labor difficulties. In no event shall any extension
affect the sixty-five year term of any lease.