Haw. Code R. § 13-190.1-23 - Permit application approval
(a) The permit
application will be reviewed for compliance with the requirements provided in
this chapter and in general accordance with standard practice for dam safety.
If an application is incomplete or defective, it shall be returned to the
applicant. The application shall be corrected and returned to the board within
ninety days or such further time as may be given by the department in order to
retain its validity. If the application is not returned within the required
time limit, it shall be deemed automatically rejected.
(b) After the department has determined that
the application is complete and the plans and specifications conform to this
chapter and generally accepted engineering practice, the board shall approve
the plans and specifications and issue an application approval with any
conditions determined to be appropriate by the board.
(c) Actual construction, enlargement, repair,
alteration, or removal shall be commenced within the time frame set by the
board in the application approval; otherwise, the application approval becomes
void. The department may, upon written application and for good cause shown,
extend an owner's time for commencing construction, enlargement, repair,
alteration, or removal of a dam or reservoir.
(d) Actual construction, enlargement, repair,
alteration, or removal of a dam or reservoir shall be completed with five years
of issuance of the application approval unless an extension authorized in
writing by the board is issued.
(e)
The board decision under subsection (b) shall be made within 180 days of the
receipt by the department of a complete application package.