Haw. Code R. § 13-190.1-30 - General construction requirements for construction, enlargement, repair, alteration, or removal of a dam, reservoir, or appurtenant works
For the actual construction work for the construction, enlargement, repair, alteration, or removal of a dam, reservoir, or appurtenant works, the owner or applicant, or both, shall be responsible for providing and complying with the following:
(1)
Construction engineer's observation of construction.
(A) Prior to the start of any work on the dam
or reservoir, the owner or applicant shall provide a construction engineer, to
ensure compliance with the approved plans and specifications, including any
approved change orders and the construction quality assurance plan;
(B) The construction engineer shall have
ultimate responsibility for the supervision of all inspection tasks and
compliance with approved plans and specifications; and
(C) The construction engineer may assign some
inspection tasks to a duly authorized agent, under the construction engineer's
supervision;
(2) A
construction quality assurance plan. A construction quality assurance plan
shall be prepared and submitted to the department at least thirty days prior to
the start of construction, which details the minimum requirements of the
construction engineer's observation of construction. The minimum components of
this plan shall include the following as applicable:
(A) Listing of parties and their roles and
responsibility;
(B) Names and
qualifications of the engineer(s) and staff to be used on the
project;
(C) Anticipated
construction observation schedule for the construction engineer and
staff;
(D) Schedule of observations
and inspections (with reference to specification sections), such as the
observation of the foundation or other inspections, as deemed appropriate by
the department or design engineer;
(E) Schedule of required submittals,
including shop drawings (with reference to specification section);
(F) Schedule of construction material tests
(with reference to specification section); and
(G) Schedule of construction performance
tests (with reference to specification section);
(3) Construction records. The construction
engineer shall maintain a record of construction that, at a minimum, shall
include: daily activity and progress reports; all test results pertaining to
construction; photographs sufficient to provide a record of foundation
conditions and various stages of the construction through completion; all
geologic information obtained; and construction problems and
remedies;
(4) Construction
schedule;
(5) Construction
emergency action plan;
(6) Labor
and material bonds. Where the project construction estimate exceeds $500,000
(including design), the owner shall furnish evidence of a bond for labor and
materials for the approved construction or alteration work, unless otherwise
allowed by the board;
(7) General
liability insurance. Insurance coverage must be maintained for the minimum
amounts stipulated by the department, with a provision identifying the
department as an additional insured, and evidence of insurance provided to the
department prior to the start of construction;
(8) Change order requirements. When
unforeseen site conditions or material availability require that the
construction work differ significantly from the approved plans and
specifications, a change order, including details, must be provided by the
construction engineer to the department:
(A)
No change shall be executed until approved by the department;
(B) Major changes must be submitted in
writing with supporting documentation, and approved in writing by the
department;
(C) If the department
determines that the proposed construction change order represents a significant
modification of the application approval that could have an effect on
structural integrity or safe operations of the project, then approval of the
change order by the board or department shall be required;
(D) If board approval of the proposed
construction change order is required, no action can be taken by the owner to
make the construction change until approval is given by the board;
and
(E) Minor changes may be
transmitted verbally by the construction engineer and. approved by the
department verbally, provided documentation of the change is provided to the
department within ten days of the approval;
(9) A pre-construction meeting shall be held
subsequent to submitting the construction observation and quality assurance
plan, but not later than fourteen days prior to start of construction. All
parties actively involved in the construction should be requested to attend,
such as the dam owner, the design engineer, the construction engineer, the
contractor, and the department. At a minimum, the following should be
discussed:
(A) Project personnel and roles:
(i) Project communication protocol between
the owner, construction engineer, and the department shall be established at
the pre-construction meeting; and
(ii) The names of the contractors and any
principals in charge shall be furnished to the department at the
meeting;
(B) Project
schedule;
(C) Special issues:
(i) The means used to divert and carry
inflows into the reservoir;
(ii)
Reservoir filling requirements; and
(iii) Special permitting
requirements;
(D) The
contractor's quality control plan, developed by the contractor shall be
thoroughly explained, including but not limited to the following:
(i) Identification of the firm that will
conduct the construction material tests in the field and in the
laboratory;
(ii) Schedule of
required submittals, including shop drawings (including ' reference to
specification ' section);
(iii)
Schedule of construction material tests (including reference to specification
section);
(iv) Schedule of
construction performance tests (including reference to specification
section);
(v) Schedule of
notifications to the engineer and the department; and
(vi) Plan for addressing construction
difficulties.
(E) Change
order procedures;
(F) Maintenance
of records;
(G) Notifications- and
submittals; and
(H) Construction
progress reports;
(10)
Reservoir fill'ing plan.
(A) A schedule for
the filling of the reservoir specifying the fill rates, water level elevations
to be held for observation, and a schedule for inspecting and monitoring the
dam;
(B) Upon written request by
the owner and for good cause shown, the department may temporarily approve
storage of water prior to full compliance with the acceptance of construction.
Only a partial reservoir filling will be granted and final acceptance of the
construction for full use will not be granted until all the construction
completion documents have been satisfactorily completed. The written request
shall include:
(i) A schedule for the filling
of the reservoir specifying the fill rates, water level elevations to be held
for observation, and a schedule for inspecting and, monitoring the
dam;
(ii) A draft emergency action
plan; and
(iii) A draft operation
and maintenance plan;
(11) Completed project documentation.
(A) Submission of required documentation as
detailed in section 13-190.1-31;
(B) Topographic survey of completed work
including all monuments, inverts, crest alignment, spillways, and significant
appurtenant features, when required by the department;
(12) Notifications to the department. The
construction engineer shall notify the department of the following:
(A) The date of the start of
construction;
(B) Notice for
inspection(s), The construction engineer shall give the department at least
ten days advance notice of initial materials placement on the dam's foundation,
in the cutoff trench, outlet backfill, outlet foundation, and any appurtenance
requested by the department in the approval of the plan for construction
observation, to allow for observation by the department;
(C) Notice of substantial completion shall be
issued by the construction engineer to the department stating that the
permitted improvements are functionally complete such that filling of the
reservoir can be accomplished;
(D)
Notice of final inspection. The construction engineer shall give the department
fifteen days advance written notice prior to the project's final construction
inspection;
(E) Notice of start of
reservoir filling. The construction engineer shall provide notice at least ten
days prior to initiating filling of the reservoir, unless otherwise agreed upon
at final inspection. Filling of the reservoir shall not commence until
concurrence is received from the department;
(13) Suspension of construction or revocation
of permit.
(A) Unsafe conditions. If
conditions a-re'. revealed which will not permit the construction, enlargement,
repair, alteration, or removal of a safe dam or reservoir, the application
approval for construction, enlargement, repair, alteration, or removal shall be
revoked;
(B) Violation of
application approval. If at any time during construction, enlargement, repair,
alteration, or removal of a dam or reservoir the department finds that' the
work is not being done in accordance with approved plans and specifications,
the department shall give a written notice thereof to the owner.
(i) The written notice shall state the
specific violations or deficiencies and shall order the immediate compliance
with the approved plans and specifications;
(ii) The department may order that no further
work be done until compliance has been effected and confirmed by the department
or its designated representative;
(iii) If the owner fails to comply with the
department's written notice or the approved plans and . specifications, the
board shall revoke the application approval and compel the owner to remove the
incomplete structure sufficiently to eliminate any safety hazard to life or
property.