Haw. Code R. § 13-190.1-50 - Dam permit application fees for construction, repair, alteration, or removal
(a) The applicant
or owner shall submit with the application for construction, enlargement,
alteration, repair, or removal of a dam or reservoir, an application fee in the
amount equal to two per cent of the estimated cost of construction, including
engineering costs.
(b) For the
purposes of this subchapter, the estimated cost of the construction,
enlargement, alteration, repair, or removal shall include the following:
(1) The cost of all labor and materials
entering into the construction of the dam and appurtenant works or
reservoir;
(2) The cost of
preliminary investigations and surveys;
(3) The cost of the construction plans
properly chargeable to the cost of the dam or reservoir; and
(4) Any and all other items entering directly
into the cost of the construction, enlargement, alteration, repair, or
removal.
(c) The costs
of right-of-way, detached powerhouses, electrical generating machinery, and
roads and railroads affording access to the dam or reservoir shall not be
included among the items used in the determination of cost.
(d) An application shall not be considered by
the department until the application fee is received.'
(e) In the event the actual cost exceeds the
estimated cost by more than fifteen per cent, a further fee shall be required
by the board before final approval and shall be two per cent of the amount the
actual cost exceeded the estimated cost of the construction, enlargement,
alteration, repair, or removal. No further fee shall be required, if such fee
is to be computed at less than twenty dollars.