Haw. Code R. § 15-150-19 - Emergency approvals
(a) In case of
emergency repairs to existing public utilities including, but not limited to,
flood control structures, water, sewer, gas, and electric transmission lines,
and highways, the respective governmental agency or public utility company is
exempted from obtaining a special management area use approval pursuant to the
requirements of this chapter. Two reports of any repair projects, valued in
excess of $500,000, shall be recorded with the lead agency, one within three
days after the start of the project and the other upon its
completion.
(b) In the event a
disaster is impending or has been declared under county law, or under chapter
127 or 128, HRS, the requirements of this subchapter shall be waived.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.