Haw. Code R. § 19-1-28 - Granting or denying of application
(a) Unless
otherwise provided by law, the department shall grant or deny an application
for a business or development-related permit, license, or approval, within
ninety days of receipt by the department of the properly completed application.
Unless otherwise provided, if the department does not take action to grant or
deny the application within the ninety-day deadline, the application shall be
deemed approved. This deadline shall not apply to applications that are subject
to state administered permit programs delegated, authorized, or approved under
federal law. When an environmental impact statement is required pursuant to
chapter 343 of the Hawaii Revised Statutes or when a contested case hearing is
requested pursuant to chapter 91 of the Hawaii Revised Statutes the application
shall not be deemed to be completed until the department receives satisfactory
verification of the acceptance or nonacceptance of the final environmental
impact statement or the decision on the contested case hearing.
(b) The maximum period of time, including any
extension established, pursuant to this section shall be extended in the event
of a national disaster state emergency, or union strike which would prevent the
applicant, the agency, or the department from fulfilling application or review
requirements.