The following fees are due and payable at the time an application is made for a permit. The minimum fee is $10; it shall not be refundable even if the applicant, after the issuance of the permit and payment of the fee, decides not to proceed with the construction. The minimum fee of $10 covers administrative costs, such as the cost of processing the permit and reviewing the construction plans.
(1)
Schedule I - The fee for a permit to trench for installations such as
pipelines, underground cables, and ditches:
(A) Tor the first 20 lineal feet of trench,
50 cents per lineal foot.
(B) For
the balance of the trench, 10 cents per lineal foot,
(2) Schedule II - The fee for the permit for
all other construction such as for driveways and subdivision road connections:
(A) For the first 20 square yards, 50 cents
per square yard.
(B) For the
balance of the area, 10 cents per square yard.