Haw. Code R. § 19-105-19 - Use and occupancy agreements
(a) On active and
completed state highway projects, the use and occupancy of the highway
rights-of-way by utility facilities shall be in accordance with the prescribed
policies and procedures of the Federal Highway Administration Federal-aid
Highway Program Manual (FHPM)
1-4-4
and 6-6-3-2.
(b) Where utility
facilities are to cross, or otherwise occupy, the right-of-way of an active or
completed state highway project, the state and the utility shall agree in
writing as to the terms of such use and occupancy, and the manner in which such
facilities are to be accommodated thereon.
(c) The cost of any future removal,
relocation, replacement, reconstruction or adjustment of utility facilities
shall be in accordance with the provisions of section
264-33,
Hawaii Revised Statutes.
(d) Where
the utility proposes to install its utility facilities within any right-of-way
of an active state highway project prior to the completion of final plans for
the highway project, it is the policy of the department of transportation to
deny the issuance of the permit required to be taken by the utility company or
in the alternative require the utility company to await the completion of final
plans for the project; unless the utility company shall agree in writing to
bear the entire cost of the later relocation of any utility facility installed
in the right-of-way if the relocation should become necessary during the
initial construction of the highway project and waive any and all right to
participation for such future relocation under existing or subsequent statutes
as a result of the initial construction of the highway project.