Haw. Code R. § 19-170-196 - Construction procedures
(a) The subdivider
shall notify the executive officer at least one week in advance of the date the
subdivider will begin construction, of the contractor's name, contract price,
construction schedule, and any other pertinent information, and shall file four
sets of prints of the approved construction plans with each of the following:
the division of engineering and division of sewers of the department of
wastewater management, division of traffic planning and division of street
lighting of the department of transportation services, the board of water
supply, and the department of recreation; and one print with the executive
officer.
(b) Every three months,
the subdivider shall report the status of construction to the executive officer
indicating progress and the work remaining.
(c) At any stage of construction and prior to
approval of improvements, if the executive officer, or his or her designee,
find that any of the work is likely to create problems jeopardizing property or
public safety, they may require a temporary stopping of work, plan revisions,
or remedial work procedure changes such as limiting the area which may be
graded or developed at one time.