(a) The executive
officer may require, at his discretion, prior to receipt of any application for
a development permit, a project eligibility review of the development project
to consider the project concept and its impact on infrastructure facilities
such as streets, pedestrian and bicycle circulation, sanitary sewers, drainage
and water, and to improve efficiency and avoid unnecessary delays and expense
in processing the formal development application. If the executive officer
determines that project eligibility review is required, no development
application shall be considered until such review has been completed.
(b) To conduct project eligibility review,
the applicant shall provide such information as the executive officer may
request in his discretion, including without limitation, the proposed site
plan, basic massing, floor area allocation and location of proposed uses,
off-street parking and loading, pedestrian and vehicular circulation, and
location of existing and proposed improvements and utilities.
(c) To the extent possible, project
eligibility review shall be completed within thirty days of the executive
officer's determination to require the review.
(d) Development shall not be approved unless
adequate infrastructure facilities are or will be made available to service the
proposed development prior to occupancy. The executive officer may consult with
applicable governmental agencies regarding the adequacy of infrastructure
requirements. Any development approval may be subject to such conditions as the
corporation may impose under these rules, including without limitation, the
requirement that the concerns and requirements of appropriate governmental
agencies relative to the adequacy of infrastructure facilities for the proposed
development are satisfied.
(e)
Notwithstanding a requirement for a project eligibility review, potential
applicants may seek preliminary review of their proposed developments with the
executive officer prior to submitting an application for a development
permit.
(f) Approval of
construction plans by ATDC shall constitute a determination that the project
has met the project eligibility review requirements herein.