Haw. Code R. § 6-74-18 - Availability of electric utility system cost data; special rule for small electric utilities
(a) Each electric
utility shall:
(1) Provide comparable data to
that required under § 6-74-17 as is reasonably available to enable
qualifying facilities to estimate the electric utility's avoided costs for
periods described in §6 74-17;
(2) With regard to an electric utility which
is legally obligated to obtain all its requirements for electric energy and
capacity from another electric utility, provide the data of its supplying
utility and the rates at which it currently purchases such energy and capacity;
and
(3) Submit comparable data as
required under §6 74-17, when the electric utility files an application
for increase, particularly with respect to the calculation of avoided energy
costs, to enable qualifying facilities to estimate the electric utility's
avoided costs for the periods described in § 6-74-17.
(b) If any such electric utility fails to
provide information required in subsection (a) within one hundred twenty days
of a request, the qualifying facility may apply to the commission for an order
requiring that the information be provided. If, after receiving such a request
for data, the electric utility applies for commission determination of the
qualifying status of the facility pursuant to § 6-74-8, the time for
providing such information shall be suspended until the commission determines
such status.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.