Ill. Admin. Code tit. 17, § 3040.50 - Eligible Project Costs
a)
Grant assistance may be otained for the following items:
1) Land acquisition costs (fee simple title,
permanent easement or long-term lease) for bicycle paths, including associated
appraisal costs approved by the Department. For acquisition of less than fee
simple title or permanent easement, such as a lease agreement, the agreement
must cover a minimum time period of 25 years, unless otherwise approved by the
Department. The Department will consider, on a case-by-case basis, lease
arrangements for shorter periods when State statute prohibits a unit of local
government from entering into such a long-term agreement, or other
circumstances beyond the control of the local unit of government prohibit such
arrangements to assure the land lease is not rescinded prior to the terms of
the amortization schedule in the project agreement being fulfilled. For
example: statutory limitations prevent longer than five year lease, but lease
is automatically renewable.
2)
Bicycle path development costs including, but not necessarily limited to, site
clearing and grading, surfacing, drainage, bridging, access control devices,
fencing, signs and associated support facilities such as parking areas, access
roads, shelters, restrooms, safety lighting, potable water supply and other
directly related bicycling support facilities. Architectural/engineering
services deemed necessary for the proper design and construction of project
bicycle paths are also considered eligible development costs.
b) Project costs for which
reimbursement is sought cannot be incurred by the project applicant until after
grant approval notification. Costs incurred prior to Department approval are
ineligible for grant assistance. For acquisition projects, costs are considered
incurred when property deed, lease or other conveyance is accepted by the local
sponsor or first payment is made on the project property or to an escrow
account/agent for the property. In addition, no purchase agreement, option,
etc., or price negotiations shall be entered into prior to Department approval.
Development project costs are considered incurred on the date construction
contracts are signed or actual physical work begins on the project site or
project materials are delivered.
c)
No grant awards shall be awarded for the acquisition or development of land
which will not be available for public bicycling use.
Notes
Amended at 22 Ill. Reg. 4902, effective March 2, 1998
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.