Ill. Admin. Code tit. 17, § 3702.70 - Application for Permit to Remove Dams - Contents
Application for a permit to remove a dam shall be made on forms provided by OWR. Separate applications are required for each dam. The application shall include, as a minimum:
a) Plans and documents, sealed, signed and
dated by an engineer, stating that the design documents have been prepared
under the engineer's personal supervision and are in conformance with this
Part.
b) Computations for design of
the method and timing for dewatering the reservoir.
c) Design plans and computations to effect
the breach, including size of breach, shape of breach and disposal of spoil
material.
d) Plans and computations
for controlling erosion at the site of the breach during and after the
breach.
e) Computations detailing
the effects of the breach on the channel downstream of the breach.
f) Plans and computations for restoring the
channel upstream of the breach.
g)
Plans and computations for control of sediment deposits in the
reservoir.
h) Plans for the
restoration of the bed of the reservoir.
i) Plans for maintenance of the breach,
downstream and upstream channels, and reservoir bed.
j) A time schedule for initiation and
completion of all phases of the removal of the dam operation.
k) Agreement of the applicant to provide
as-built plans upon completion of removal. These plans shall be signed by the
engineer or other qualified personnel who was responsible for inspection during
the removal.
l) Right of access
authorization for the OWR to inspect the breach site and vicinity before,
during and after breaching operations and until restoration of the stream and
impacted area is complete.