Ill. Admin. Code tit. 17, § 3708.140 - Time to Permit Issuance; Emergency Authorizations; Duration; Revisions
a) If permit
authority has not been delegated to a municipality or county, the Department,
pursuant to Sections 3708.70 and
3708.110, will either grant
approval or approval with conditions or deny an application for permit within
90 days after receipt of a complete application (or 150 days in the event a
hearing is held) unless a longer time period is requested in writing by the
applicant. If the Department has not approved the application within these time
limits, the application will be deemed denied. The time limit for final
Department action on a permit application will be computed from the date on
which the Department has received all information required in Section
3708.110. If additional data or
revised plans are required by the Department, the time between the request and
receipt of the requested material will not be counted in these time periods.
Also, the time required for resolution of relevant objections (see Section
3708.120) will not be counted in
these time periods.
b) The
Department will issue an emergency permit after receipt of a properly executed
application form (including an explanation of why the work to be performed is
of an emergency nature) and plan sheets describing the work if harm to life or
loss of property is likely to occur if initiation of the activity is delayed.
An applicant for an emergency permit is deemed to have agreed to make
modifications, at his or her own expense, required by the Department if the
work does not comply with Section
3708.70, based upon completion
of a review and on comments received during the public comment period, to bring
the activity into compliance with this Part.
c) Permits will be valid until December 31 of
the third year following the date of permit issuance, unless the Department
determines that the proposed work must be completed sooner, such as in the case
of work to correct a violation. Upon the written request of the applicant,
permits may be granted for longer periods of time if the expected construction
period exceeds three years.
d) If
the permitted activity is not completed by the expiration date of the permit,
the permittee shall submit a written request that the expiration date be
extended if the permittee intends to pursue the permitted activity. Upon
receipt of the request, the Department will extend the expiration date if the
permitted activity is in compliance with the rules of the Department at the
time of the request.
e) If, after
permit issuance, the permittee decides to revise the approved plans, the
permittee shall submit those revised plans to the Department, along with a
written request for approval. If the Department determines that the revised
plans are in compliance with this Part, an approval of revised plans will be
issued to the permittee.
Notes
Amended at 38 Ill. Reg. 983, effective December 27, 2013