Ill. Admin. Code tit. 23, § 3035.540 - Supervision of Public Library Construction Act Projects
The State Librarian shall exercise general supervision over public library construction projects financed pursuant to the Act.
a) The grantee library will expend in 30%
increments. The public library shall submit a letter from an architect and a
financial report at the 30, 60 and 90% points of substantial completion. The
final 10% will be paid out upon completion of the project and submission of all
final reports to the State Librarian.
b) Construction work will be performed under
the lump sum (fixed price) contract method.
c) The library will publicly announce all
requirements for architectural, engineering and land surveying services and
procure these services on the basis of demonstrated competence and
qualifications and negotiate contracts at fair and reasonable prices, in
accordance with the Illinois Local Library Act [75 ILCS 5/5-5
] and the Illinois Library District Act [75 ILCS
16/40-45 ].
d) Architectural, engineering and land
surveying contracts will be made in accordance with the Local Government
Professional Services Selection Act [50 ILCS 510 ].
e) Adequate methods of obtaining competitive
bidding will be employed prior to awarding the construction contract by public
advertising in a newspaper of general circulation in the area, and the award of
the contract will be made to the responsible bidder submitting the lowest
acceptable bid, in accordance with the Illinois Local Library Act and the
Illinois Library District Act. A copy of the advertisement, with verification
of the date of publication and name of the newspaper, shall be submitted to the
Illinois State Library within 10 days after publication.
f) No person or business shall bid, offer,
make a submission, or enter into a contract with the grantee if the person or
business assisted the grantee or any agent or employee of the grantee, who by
the nature of his or her duties has the authority to participate personally or
substantially in the contract specifications, requests for bids or proposals,
or otherwise by reviewing, drafting, directing, or preparing any invitation for
bids, a request for proposal, or request for information or provided similar
assistance except as part of a publicly issued opportunity to review drafts of
all or part of these documents. This subsection does not prohibit a person or
business from submitting a bid or offer or entering into a contract if the
person or business:
1) initiates a
communication with an employee to provide general information about products,
services, or industry best practices;
2) responds to a communication initiated by
an employee of the Library for the purposes of providing information to
evaluate new products, trends, services, or technologies; or
3) asks for clarification regarding a
solicitation, so long as there is no competitive advantage to the person or
business and the question and answer, if material, are publicly posted and made
available to other bidders or offerors as an addendum to the
solicitation.
g) When,
for any reason, any vendor, bidder, offeror, potential contractor, contractor,
or other person suspects collusion or other anti-competitive practice among any
bidders, offerors, potential contractors, contractors, or employees of the
State, that person shall transmit a notice of the relevant facts to the State
Librarian.
h) All laborers and
mechanics employed by the contractor or subcontractors on all construction
projects shall be paid wages at rates not less than those prevailing on similar
construction in the locality, as determined by the Illinois Department of Labor
in accordance with the Prevailing Wage Act [820 ILCS 130 ].
i) A copy of the building permit shall be
supplied to the State Librarian prior to the actual construction, and the
permit shall be posted in a prominent place on the construction site.
j) Any change in the Plans and Specifications
requiring a work change order shall be submitted to the State Librarian. All
change orders shall be subject to the Illinois Public Works Contract Change
Order Act [50 ILCS 525 ]. The State Librarian shall be notified of and approve
or deny any change orders of $20,000 or more and the modification of any public
areas of the grantee library from the proposed original plans of the approved
grant application. The change order will be accompanied by a letter approved by
the library board stating that there is no adverse impact on library services.
Change orders do not affect the grant award amount.
k) Contractors and subcontractors shall
comply with:
1) all applicable provisions of
the Illinois Human Rights Act [775 ILCS 5 ];
2) all federal and State laws, rules and
regulations that prohibit discrimination because of race, color, religion, sex,
marital status, national origin, ancestry, age and physical or mental
disability; and
3) the conflict of
interest provisions specified in the Illinois Procurement Code [30 ILCS 500
].
l) Construction
contracts shall be signed by both the library board and contractors, using the
Standard Form of Agreement Between Owner & Contractor A101- 2007, published
by the American Institute of Architects, 1735 New York Ave., NW, Washington DC
20006-5292, or a comparable format. No later amendments to this form are
incorporated in this Section. Contracts are to be submitted to the State
Librarian prior to the start of construction. All subcontractors are to perform
work in accordance with the conditions and standards contained in the contracts
signed by the library board and the State Librarian. The State Librarian shall
have the right to disapprove any contracts between the library board and
contractors if:
1) The bidding procedure
outlined in subsection (e) was not followed.
2) The conditions and standards specified in
the contract between the State Librarian and the library board are not
incorporated into the contracts between the library board and the
contractors.
3) The requirements of
subsections (f) and (k) were not followed.
m) Grant monies awarded are based on the
amount specified in the original budget in the grant application; grant awards
will not be increased because of subsequent increases in project costs.
Decisions shall not affect the time frame imposed unless approved by the
Director of the State Library.
n) A
sign will be displayed on the construction site stating that State funds
administered by the State Librarian are being used for the construction and
that a plaque will be placed in the completed building stating that State funds
administered by the State Librarian were used for the building's
construction.
o) Any agent
authorized by the State Librarian, upon presentation of credentials and in
accordance with the constitutional limitation on administrative searches, shall
have full access to, and the right to examine, any records, books, papers or
documents of the grantee involving transactions related to the grant.
p) Construction shall not begin until a
contract is executed with the State Librarian.
q) Construction will commence within 140 days
after the effective date of the grant contract. Construction may not commence
until proof of ownership or long-term lease agreement of the affected real
estate is received.
r) The
following reports and records will be completed and transmitted to the State
Librarian: quarterly narrative and financial reports; notification within 15
days after completion of the project; a close-out report that is a final
financial and narrative report within 36 months after the execution of the
contract, unless an extension is granted by the State Librarian; and other
reports and documents, such as prevailing wage rates and receipts to verify
vouchers, as reasonably may be required by the State Librarian. The final
financial report shall be signed by the president of the library's board of
directors.
1) Financial reports shall show:
the amount of authorized State and local funds; interest earned on grant funds;
expenditures made from grant funds and from interest earned on grant funds;
obligated funds, by amount of line item remaining compared to the original
budget.
2) Narrative reports shall
state: the progress of the project; accomplishments to date; problems
encountered; objectives met and unmet; changes implemented; and the percentage
of completion of the project to date.
3) The close-out report shall evaluate the
degree to which the grantee achieved the goals and objectives of the project.
The close-out report shall include a project audit according to Section
3035.140(e).
4) For a project that requires an architect
or engineer, the architect or engineer shall certify to the State Librarian
when the project reaches the 30%, 60%, 90% and 100% stage of
completion.
s) When
construction is complete, sufficient funds will be available for effective
operation and maintenance of the facilities, in accordance with applicable
federal, State and local requirements.
t) The library shall establish a separate
account for construction grant funds with a federally or Illinois regulated
financial institution that is insured by the Federal Deposit Insurance
Corporation.
u) Any interest earned
on the grant funds will be expended, without limitation or exception,
exclusively on the public library construction project.
v) Some of the documentation and assurances
in this Section may be waived or modified by the State Librarian if the
applicant adheres to comparable or stricter requirements, except that
subsections (f), (g) and (k) will not be waived.
Notes
Amended at 37 Ill. Reg. 18922, effective November 7, 2013