Ill. Admin. Code tit. 35, § 170.113 - Step 3 - Submission of Project Plan
Current through Vol. 46, No. 16, April 15, 2022
a) Each applicant shall submit an overall
project plan for each medium. The project plan is a preliminary engineering
document which defines the scope of the total project and generally assembles
basic information including, for example, the following: preliminary project
layout; assumptions and design criteria; a discussion of how environmental
regulations and requirements will be met, including coordination of multimedia
interrelationships; and the project milestones. This plan, which provides the
continuing technical basis for the detailed design and preparation of final
engineering plans and specifications, shall contain, as a minimum, a discussion
of:
1) The interrelationships among the
various aspects of environmental control;
2) Selected controls;
3) Preliminary design considerations for each
medium, and for each phase if construction or development will be phased;
and
4) The timetable for project
implementation for each medium.
b) The project plan shall be submitted to the
Agency at any time but no later than at the time of submission of the project
permit application.
c) During the
review of the project plan, the agency will resolve conflicts arising out of
specific Divisional requirements.
d) The Agency will provide a written response
to the applicant within 45 days of receipt of the project plan except that when
a project plan is submitted with the permit application, it shall be considered
as part of the application.