Ill. Admin. Code tit. 35, § 371.120 - Introduction
a) A PO identifies
specific actions, related start and completion dates, and other supportive
information necessary to assure that the wastewater treatment facility and all
associated personnel are properly prepared for start-up and continued
operation. Actions identified will fulfill technical and administrative
requirements for efficient and reliable performance.
b) A PO is required for all federal grant
projects which started construction after November 29, 1976. A PO is required
for all state grant projects which started construction after August 18,
1978.
c) Plans of Operation shall
be submitted as follows:
1) One copy of the
preliminary PO must be submitted with the plans and specifications for the
project during Step 2 of the construction grants process.
2) Two copies of the final PO must be
submitted with the draft O&M Manual for the project before 50% of the grant
payment of a Step 3 grant can be made. One copy of the approved final PO will
be retained by the Agency.
3) All
POs must be submitted for review to:
Illinois Environmental Protection Agency
Division of Water Pollution Control
Grant Administration Section
2200 Churchill Road
Springfield, Illinois 62706
d) In preparing the PO, grantees are
encouraged to use their own operations staff, with input as necessary from
consulting engineers and other appropriate sources. The PO is as important to
facility operation as construction scheduling is for construction. Grantees
will be expected to keep the PO current.