a)
Monitoring
1) If a supplier submitted an IDSE
report, it must begin monitoring at the locations and during the months that
the supplier has recommended in its IDSE report submitted under Section
611.925, following the schedule
set forth in Section 611.970(c),
unless the Agency, by a SEP, requires other locations or additional locations
after its review. If the supplier submitted a 40/30 certification under Section
611.923, it qualified for a very
small system waiver under Section
611.924, or it is a NTNCWS that
serves fewer than 10,000 persons, the supplier must monitor at the locations
and on the dates identified in its monitoring plan as described in Section
611.382(f),
updated as required by Section
611.972.
2) The supplier must monitor at no fewer than
the number of locations identified in the applicable of subsections (a)(2)(A)
through (a)(2)(M), subject to the limitations of subsections (a)(2)(N) and
(a)(2)(O).
A) A Subpart B system supplier
that serves fewer than 500 persons must monitor annually at two distribution
system monitoring locations during each monitoring period.
B) A Subpart B system supplier that serves
500 to 3,300 persons must monitor quarterly at two distribution system
monitoring locations during each monitoring period.
C) A Subpart B system supplier that serves
3,301 to 9,999 persons must monitor quarterly at two distribution system
monitoring locations during each monitoring period.
D) A Subpart B system supplier that serves
10,000 to 49,999 persons must monitor quarterly at four distribution system
monitoring locations during each monitoring period.
E) A Subpart B system supplier that serves
50,000 to 249,999 persons must monitor quarterly at eight distribution system
monitoring locations during each monitoring period.
F) A Subpart B system supplier that serves
250,000 to 999,999 persons must monitor quarterly at 12 distribution system
monitoring locations during each monitoring period.
G) A Subpart B system supplier that serves
1,000,000 to 4,999,999 persons must monitor quarterly at 16 distribution system
monitoring locations during each monitoring period.
H) A Subpart B system supplier that serves
5,000,000 or more persons must monitor quarterly at 20 distribution system
monitoring locations during each monitoring period.
I) A groundwater system supplier that serves
fewer than 500 persons must monitor annually at two distribution system
monitoring locations during each monitoring period.
J) A groundwater system supplier that serves
500 to 9,999 persons must monitor annually at two distribution system
monitoring locations during each monitoring period.
K) A groundwater system supplier that serves
10,000 to 99,999 persons must monitor quarterly at four distribution system
monitoring locations during each monitoring period.
L) A groundwater system supplier that serves
100,000 to 499,999 persons must monitor quarterly at six distribution system
monitoring locations during each monitoring period.
M) A groundwater system supplier that serves
500,000 or more persons must monitor quarterly at eight distribution system
monitoring locations during each monitoring period.
N) The supplier must monitor during month of
highest DBP concentrations.
O) A
supplier on quarterly monitoring must take dual sample sets every 90 days at
each monitoring location, except for a Subpart B system supplier that serves
500 to 3,300. A groundwater system supplier that serves 500 to 9,999 persons
which is on annual monitoring must take dual sample sets at each monitoring
location. Any other supplier that is on annual monitoring or which is a Subpart
B system supplier that serves 500 to 3,300 is required to take individual TTHM
and HAA5 samples (instead of a dual sample set) at the locations with the
highest TTHM and HAA5 concentrations, respectively. For a supplier that serves
fewer than 500 people, only one location with a dual sample set per monitoring
period is needed if the highest TTHM and HAA5 concentrations occur at the same
location and month.
3) If
a supplier is an undisinfected system that begins using a disinfectant other
than UV light after the dates set forth in Subpart W for complying with the
IDSE requirements, the supplier must consult with the Agency to identify
compliance monitoring locations for this Subpart Y. The supplier must then
develop a monitoring plan under Section
611.972 that includes those
monitoring locations.