The CQA officer shall exercise professional judgement to certify the following:
a) The bedding material contains no undesirable objects;
b) The placement plan has been followed;
c) The anchor trench and backfill are constructed to prevent damage to the geomembrane;
d) All tears, rips, punctures, and other damage are repaired; and
e) All geomembrane seams are properly constructed and tested in accordance with manufacturer's specifications.